September 2000 Newsletters

 

Katz & Stone, L.L.P. Construction Newsletter
September/October 2000
Volume X, Number V

 

SUBCONTRACTORS SUCCESSFULLY SUE ARCHITECT FOR CERTIFYING PAYMENTS TO AN UNBONDED GENERAL CONTRACTOR

Architects who have negligently performed their contractual obligations on a construction project are often insulated from the claims of injured contractors and subcontractors by the lack of contractual privity between the parties.  In the case of Gary Boren d/b/a Reliable Plumbing v. Thompson & Associates, 999 P.2d 438 (Okla. 2000), the Supreme Court of Oklahoma rejected just such an argument, finding a public-project architect liable to multiple unpaid subcontractors for negligently certifying payments to the general contractor with knowledge that the general contractor had not secured a payment bond as required by state law.

In Gary Boren, the Tyrone City school board hired Thompson and Associates (the "architect") to design and oversee construction of a new library building.  Russell McBee (the "general contractor") was awarded a contract for the construction of the library.  The general contractor, in turn, contracted with multiple subcontractors to provide materials and labor for construction of the library.

Oklahoma law requires general contractors to obtain both performance and payment bonds ensuring the construction of public buildings.  The payment bond serves to guarantee payment to subcontractors in the event of default.  Although the general contractor in Gary Boren obtained the required performance bond from a bonding company, it failed to obtain a payment bond.

Work on the project began in August 1994.  At that time, the architect sent the general contractor a note reminding it of the required performance and payment bonds.  In response, the general contractor sent the architect a copy of only a performance bond; no payment bond was ever sent.  The architect apparently filed the paperwork without verifying the existence of a payment bond and began certifying payments to the general contractor.

As the project proceeded, construction was delayed and multiple subcontractors were not paid by the general contractor.  In December 1994, the architect became aware that there was no payment bond in its file after one of the subcontractors requested a copy.  Although the architect temporarily withheld certification of progress payments to the general contractor, in January 1995 the architect reversed course and began certifying additional payments to the general contractor with full knowledge that the general contractor did not have a payment bond in place.

The subcontractors remained unpaid and subsequently filed suit against the architect, alleging that it was negligent in certifying payments to the general contractor in the absence of the required payment bond.  The trial court agreed with the subcontractors, overruling the architect's motion to dismiss the case.  Ultimately, the court found the architect liable for negligence and rendered a judgment in favor of the subcontractors.

On appeal, the architect argued that it could not be held liable in negligence because it had no contract with the subcontractors and, therefore, owed no duty to act for the subcontractors' benefit.  The appellate court disagreed and affirmed the trial court's judgment against the architect.

In reaching its decision, the court cited several principles.  First, architects must exercise ordinary professional skill in rendering their professional services.  Second, architects in Oklahoma  may be held liable to contractors for their negligent breach of a duty created by contract, even though those contractors  have  no direct  contractual  relationship  with  the architect.  The court found that liability for negligent breach of a contract is not dependent on the existence of a contract between the person injured and the person causing the injury.  Rather, according to the court, such liability is simply based on whether the negligent act caused the injury and whether it was foreseeable that the negligent act could harm third-parties.

Applying these principles, the court concluded that the architect in Gary Boren had a duty to refrain from paying the general contractor without the required payment bond being secured.  The architect was aware of the statutory payment bond requirement and should have been aware that no such bond had been secured.  The architect had the authority to withhold payments in the absence of a payment bond but, even after becoming aware of this, continued to authorize payments.  Given the lack of a bond, the court concluded that the unpaid subcontractors' injuries were foreseeable to the architect.

The holding of Gary Boren represents a departure from the general rule requiring contractual privity for the recovery of purely economic losses.  Because the applicability of the general privity rule varies from state to state, subcontractors outside of Oklahoma should be aware that direct legal recourse for the negligence of an architect under the same or similar facts may be unavailable in their jurisdiction.

 

ILLINOIS COURT UPHOLDS LIMITS ON SCOPE OF "ADDITIONAL INSURED" ENDORSEMENT

In American Country Insurance Co. v. Cline, 722 N.E.2d 755, 309 Ill. App. 3d 501 (1999), the Appellate Court of Illinois enforced a restrictive additional insured endorsement in a commercial general liability policy.  In doing so, the appellate court held that an insurer may narrowly limit the extent of coverage of additional insureds to liability specifically resulting from conduct of the policy holder.

In American Country, an employee of an electrical subcontractor was injured when forty feet of electrical conduit fell upon his ladder, crushing the ladder and causing the employee to fall six feet to the floor.  The employee sued the general contractor and owner on negligence theories related to allegedly unsafe worksite conditions.

The general contractor and owner sought coverage as additional insureds under the electrical contractor's general liability policy.  The insurer denied coverage and subsequently brought a declaratory action seeking a judicial determination that it had no duty to defend or indemnify the additional insureds.

The central question before the court was the enforceability of the additional insured endorsement which contained the following restriction "The coverage afforded to the Additional Insured is solely limited to liability specifically resulting from the conduct of the Named Insured which may be imputed to the Additional Insured."

The trial court found the limitation of coverage unenforceable, at least to the extent that it implied the insurer had no duty to defend, citing the general rule that "a court is supposed to resolve any doubt about a duty to defend in favor of the insured." The insurer appealed.

On appeal, the appellate court reversed the trial court and enforced the limitation in the endorsement, stating that Illinois law favors (1) freedom of contracting between competent parties and (2) interpretations of contract clauses which favor enforceability.  In this case the court noted that the additional insured endorsement was added to the subcontractor's policy for a single $150 premium.  In exchange, the subcontractor received an "unlimited number of  'blanket' additional insurance endorsements for a single $150 premium." Thus, the court found  that for this small additional premium, it was only logical  "that the additional insureds would only receive coverage for a narrow class of claims."

In the final analysis, the court held that since the additional insureds were sophisticated parties, it was reasonable to assume that they could have negotiated any issues pertaining to insurance coverage prior to executing the subcontract.  Thus, the court held the additional insureds were bound by the terms of the endorsements.  Under those terms, since no wrongful conduct on the part of the subcontractor was alleged, the policy did not cover the additional insureds and the subcontractor's insurer had no duty to defend the additional insureds.

As a practical matter, American Country illustrates the importance of closely examining all underlying insurance policy documents when coverage is purportedly being provided by a third-party.  As the additional insureds discovered in American Country, the mere fact that one is named as an "additional insured" under a subcontractor's general liability policy is no guarantee that the coverage being provided is consistent with that which has been contractually promised.  As is evident from the result, the failure of the additional insureds in American Country to properly investigate the scope of coverage being provided by their subcontractor later proved to be a costly mistake.

 

 

4th CIRCUIT HOLDS LACK OF FORMAL TERMINATION DOES NOT BAR PERFORMANCE BOND CLAIM

A performance bond serves as a guarantee that work that is the responsibility of the surety's principal will be performed.  The bond typically sets forth: (1) the scenarios which trigger the surety's guarantees under the bond; and (2) the means by which the bond obligee may then secure completion of the principal's work.  In Siegfried Construction, Inc. v. Gulf Insurance Co. et al., 2000 U.S. App. Lexis 1304 (4th Cir. Feb. 2, 2000), the Fourth Circuit Court of Appeals considered whether the bond obligee must strictly comply with the terms of the bond in order for the surety to be held liable under the bond.

In Siegfried, a subcontractor contracted to perform drywall and other work in the construction of a hotel in Rockville, Maryland.  The subcontractor's surety issued a performance bond on behalf of the subcontractor which provided that, whenever the subcontractor "shall be, and be declared by [the general contractor] to be in default under the subcontract, . . . [the general contractor], after reasonable notice to Surety may . . . arrange for the performance of [the subcontractor's obligation under the subcontract . . . ."

In response to poor performance and delays caused by the subcontractor, the general contractor sent the subcontractor a first and second "Notice of Termination for Failure to Perform," each detailing deficiencies in the subcontractor's work and threatening termination unless corrective actions were taken.  When the corrective actions did not take place, the general contractor then sent a follow-up to the second notice, advising that it intended to exercise its right to supplement the subcontractor's workforce in order to complete the work.  Thereafter, the general contractor sent the surety copies of the Notices of Termination and a "Notice of Claim," in which the general contractor alerted the surety to its threat to terminate the subcontractor, its supplementation of the subcontractor's workforce, and the likelihood that it would seek reimbursement of its costs in completing the subcontractor's work.  In discussing its claim with the surety's investigator, the general contractor reiterated its request for help from the surety to complete the subcontractor's work.  The general contractor never actually formally terminated the subcontractor.

When the surety refused to pay the general contractor's claim for the cost of completing the subcontractor's work, the general contractor brought suit against the surety.  At the conclusion of the trial, the federal district court issued a judgment for the surety on the grounds that the general contractor's "Notice of Claim" was neither a sufficient declaration of the subcontractor's default nor adequate notice to the surety of the general contractor's arrangement for completion of the subcontractor's work.  As a result, the general contractor was held to have neither met the conditions nor followed the means of completion prescribed by the bond.

On appeal by the general contractor, the Fourth Circuit reversed the lower court's judgment.  As to the bond conditions, the court held that the general contractor's repeated notices to the subcontractor, and "Notice of Claim" to the surety, advising that the subcontractor's work was defective and threatening to terminate the subcontractor for default, was a sufficient declaration of the subcontractor's default to meet the requirements of the bond.  Importantly, the Fourth Circuit held that the general contractor was not required to formally terminate the subcontractor to declare its default.

Furthermore, the court found that the "Notice of Claim" sufficiently informed the surety that the general contractor was supplementing the subcontractor's workforce and was in fact taking steps to complete the subcontractor's work.  Moreover, the court noted that the general contractor had informed the surety's investigator that it needed the surety's assistance in completing the subcontractor's work.  As a result, the Fourth Circuit concluded that the general contractor had in fact provided adequate notice of its arrangement to complete the subcontractor's work to the surety, thus complying with one of the completion alternatives prescribed by the bond.

The Siegfried decision indicates that the Fourth Circuit will not apply bond requirements against contractors narrowly, but rather will look to all surrounding circumstances for evidence of substantial compliance with those requirements.  Moreover, Siegfried rejects the notion that contractors must formally terminate subcontractors in order to invoke the protections of a surety performance bond.  It should be noted, however, that it is unclear whether all courts would decide these issues as the Fourth Circuit did.  Therefore, contractors and owners are well-advised to follow all termination procedures exactly as set forth in their bonds and contracts and/or to seek the advice of counsel.

 

MARYLAND COURT HOLDS SUBSTANTIAL COMPLIANCE WITH LICENSING REQUIREMENT IS SUFFICIENT

Building contractors must comply with licensing requirements or risk forfeiting the right to enforce contracts through the judicial system.  In Dereggi Constr. Co. v. Mate, 130 Md. App. 648 (2000), a Maryland contractor entered into a contract to build a custom home.  The contractor did not have a Montgomery County building contractor's license at the time of the agreement as required under the County's Code.  However, the contractor obtained a license before actual commencement of the construction work.  As the construction of the home neared completion, a disagreement arose between the parties.  The owner contended the contractor had failed to fully complete the home as required by the contract while the contractor claimed that additional work performed during the construction of the home remained unpaid.

The contractor filed a petition to establish a mechanic's lien to collect the amount allegedly due.  The owner then moved to dismiss the petition on the grounds that the contract was void and unenforceable because the contractor had not obtained a building contractor's license prior to entering into the contract.  The circuit court granted the owner's motion to dismiss and the contractor appealed.

In considering the contractor's appeal, the Maryland Court of Special Appeals recognized that where a statute is regulatory in nature, protects the public, and does not merely raise revenue, the unlicensed party may forfeit the right of assistance of the courts in enforcing the contract.  After considering the specific statute in question, Section 31C-2 of the Montgomery County Code, the court held the statute in question protected the public by ensuring that builders are capable of both complying with the laws and fully performing the contracts they enter.  Further, the court determined the licensing fees in this case did not merely raise revenue as the fees only reimbursed the costs of administering the Montgomery County licensing scheme.

Notwithstanding the above, the appellate court concluded that substantial compliance with the licensing statute is all that is required because the legislative purpose of the statute could be realized without enforcing all of its requirements.  In reaching this decision, the court reasoned that: (1) the criminal and civil penalties for an unlicensed contractor are sufficient incentives to draw compliance and (2) inequity and hardship would result if contractors could not obtain relief where they diligently performed a contract.

Accordingly, the Maryland Court of Special Appeals remanded the case to the lower court to determine whether the building contractor did in fact substantially comply with the licensing statute.  While the court did not provide much guidance to the lower court  as to its definition of "substantial compliance," the court suggested that compliance which "affords the public the same protection that strict compliance would offer" might be sufficient.  Thus, it remains to be determined whether a contractor's failure to obtain a contractor's license at the time of contract formation but before performance of the contract will be deemed "substantial compliance" with the statute.

The Dereggi Construction case illustrates the importance of strictly complying with contractor licensing statutes.  While Maryland requires only "substantial compliance" with its licensing requirements, other states may require strict or absolute compliance.  Given the potentially drastic consequences which could result from non-compliance, contractors must keep abreast of, and endeavor to strictly comply with contractor licensing requirements in all jurisdictions in which they operate.