Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     2    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

ON PUBLIC PROJECTS, RECOVERY FOR BREACH OF CONTRACT
IS LIMITED BY THE AMOUNT OF EXISTING APPROPRIATIONS

Under the Anti-Deficiency Act ("ADA"), "all [public] contracts for future payments of money, in advance of or in excess of existing appropriations, are void ab initio." For those contractors entering into agreements with governmental entities, it is important to ensure that the contract price has been properly appropriated prior to commencing work. But what happens when the contract includes an open-ended indemnity, i.e., an uncapped indemnity? In Insurance Company of North America v. District of Columbia, 948 A.2d 1181 (D.C. Ct. App. 2008), the D.C. Court of Appeals held that, because it would be virtually impossible for the legislature to appropriate funds for an open-ended indemnity provision, such a provision may not be enforced against a governmental entity.

In Insurance Company of North America, the District of Columbia (the "District") contracted with Kora & Williams ("K&W"), a general contractor, to perform certain work on the Union Station Redevelopment project. From the beginning, design issues delayed K&W's performance and, when it became impractical to complete on schedule, the District terminated the contract on the basis that K&W failed to make sufficient progress toward timely completion. The District then asserted a claim under K&W's performance bond, issued by Insurance Company of North America ("INA").

Although both K&W and INA disputed the validity of the District's termination of K&W, INA ultimately entered into a partial settlement agreement with the District under which INA agreed to pay the District approximately $12.9 million in exchange for the District's release of its bond claim. The settlement agreement included additional language, however, providing that, if it was determined that the District's termination of K&W "was not justified," the District would repay to K&W the settlement amount, plus interest, and would reimburse INA for its costs, fees, and expenses; that is, the partial settlement agreement included an open-ended indemnity insofar as the indemnity provision did not cap the District's liability as it related to the reimbursement of costs, fees, and expenses.

Six years after entering into the partial settlement agreement, the D.C. Contract

Appeals Board determined that the District's "default termination decision was arbitrary and capricious and an abuse of discretion and should be converted into one for the convenience of the District." Subsequently, the District consented to a judgment for the repayment of the $12.9 million, plus interest, but disputed that it owed INA for the costs, fees, and expenses incurred by INA.

INA, therefore, asserted a breach of contract claim against the District, alleging damages in the amount of $17.4 million arising from costs, fees, and expenses incurred by INA appealing the District's termination. The District raised the ADA as a defense, arguing that it would be impossible "to know at the time the contract is signed whether there are sufficient funds in the appropriation to cover the liability if or when it arises because no one knows in advance how much the liability may be."

INA argued that the ADA did not apply to the indemnification provision, but, if the ADA did apply, that the District’s Judgment and Settlement Fund included monies appropriated to cover liabilities incurred by the District, such as the open-ended indemnity contained in the partial settlement agreement. First, the Court of Appeals found that the ADA applied to the instant dispute, reasoning that, without a cap on the indemnity, it would be impossible to know how much to appropriate for this indemnity.

Moving to the next argument, the Court of Appeals declined to treat the District's general appropriation for judgments and settlements, D.C. Code §§2-402 to -404 (2001), as a sufficient appropriation under the ADA to cover INA's open-ended indemnity. The court reasoned that, because the District did not specifically appropriate money to cover the indemnity at the time of contracting, the partial settlement agreement was not a "settlement" covered by the statutory appropriation for judgments and settlements. Further, as INA did not have a judgment providing for the recovery of costs and expenses, it failed to prove that it should be a beneficiary of the District's appropriation for judgments and settlements.

The lesson of Insurance Company of North America v. District of Columbia is that, regardless of whether a contracting officer represents that it has authority to bind a governmental entity, the savvy contractor (or surety) will confirm that an appropriation has been made covering the terms of the contract. Moreover, if requesting an indemnity from a governmental entity, it would be prudent to avoid incorporating open-ended indemnities, as such a provision may not be enforceable.

<< Prev     2    Next >>