Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     2    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

VIRGINIA MECHANIC’S LIENS AND THE 150-DAY RULE

According to Virginia Code § 43-4, a mechanic’s lien claimant’s recovery is limited to the contract value of labor and material furnished “150 days prior to the last day on which labor was performed or material furnished to the job preceding the filing” of the memorandum of lien, although there are exceptions to this “150-day rule,” including, for example, retainage. Virginia courts strictly construe this statutory provision, invalidating liens which include claims for labor and material beyond the 150-day limitations period. One reason for this requirement is to protect owners from stale claims. Section 43-15 of the Virginia Code, however, provides that,

No inaccuracy in the memorandum filed, or in the description of the property to be covered by the lien, shall invalidate the lien, if the property can be reasonably identified by the description given and the memorandum conforms substantially to the requirements of §§ 43-5, 43-8 and 43-10, respectively, and is not willfully false.

(Emphasis added.) A potential issue arises, therefore, when a lien claimant mistakenly includes amounts earned outside of the 150-day limitations period in its memorandum of lien. Should a court strictly construe § 43-4 of the Virginia Code and invalidate the lien or apply § 43-15 and treat such a mistake as an inaccuracy and allow the lien claimant to pursue enforcement of its lien rights? In Smith Mountain Building Supply, LLC v. Windstar Properties, LLC, 227 Va. 387 (2009), the Virginia Supreme Court held that the inclusion of charges for materials supplied outside the 150-day limitation period in § 43-4 of the Virginia Code renders such a lien invalid and unenforceable.

In Smith Mountain Building Supply, a material supplier furnished materials to the general contractor on two projects from June 24, 2005 to March 9, 2006, with March 9, 2006 being the last day on which the material supplier furnished materials to the two residential projects. Applying the 150- day limitation period prescribed by § 43-4 of the Virginia Code, the material supplier could lien the projects for work performed from October 10, 2005 through March 9, 2006, i.e., 150 days prior to the last day of work. The material supplier timely filed two memoranda of mechanic’s liens, though mistakenly included charges for materials furnished to the projects prior to October 10, 2005.

The owner of the property filed a motion for summary judgment, asserting that the material supplier’s inclusion of sums due for materials furnished prior to October 10, 2005 rendered the memoranda of mechanic’s liens invalid. The material supplier argued that any such inclusion was a mistaken inaccuracy and that, under § 43-15 of the Virginia Code, such inaccuracy could be excused by the court.

The material supplier directed the Court’s attention to its decision in Reliable Constructors, Inc. v. CFJ Properties, 263 Va. 279 (2002), in which the court found that a lien claimant’s inclusion of a fine in its memoranda of liens constituted an inaccuracy within the meaning of § 43-15 and that the

inaccuracy was not willfully false. The material supplier argued that the inclusion of charges for materials furnished to the projects prior to October 10, 2005 was an equivalent inaccuracy.

The court rejected the lien claimant’s argument, distinguishing Reliable Constructors from the instant appeal on the basis that, in Reliable Constructors, the court focused on the nature of the sum erroneously included in the memorandum of lien. The court reasoned that a fine is not a sum due for labor performed or materials furnished and, therefore, could not be recovered in a mechanic’s lien action regardless of the 150- day rule. In Smith Mountain Building Supply, by contrast, the inaccuracy in the material supplier’s lien was the sum claimed for materials furnished to the projects, an issue directly addressed in § 43-4 of the Virginia Code. Accordingly, this inaccuracy violated the express requirements of § 43-4 of the Virginia Code.

The lesson to be learned from Smith Mountain Building Supply is that, in pursuing a mechanic’s lien, a lien claimant risks total invalidation of its lien if it claims sums due from beyond the 150-day limitations period. Lien claimants should be careful in preparing a memorandum of lien, cognizant of the effect that including sums due for stale work may have on their lien rights.

_____________________________
(continued from page 1)

In Virginia, the running of the statute of limitations is considered to be a right enjoyed by defendants. The Virginia Supreme Court has stated that “[t]he immunity from suit that arises by operation of the statute of limitations is as valuable a right as the right to bring the suit itself.” Consequently, the protection of the statute of limitations is considered a “right” which the subcontractor enjoyed under the flow down provision of the prime contract between Skanska and DRMC. Moreover, any language in the prime contract regarding the statute of limitations becomes part of the subcontract by virtue of the subcontract’s incorporation of all prime contract documents into the subcontract. As a result, any act or omission on the part of the subcontractor is treated the same for statute of limitations purposes as an act or omission on the part of the general contractor. In this case, the statute of limitations began to run on the substantial completion date, August 19, 2002.

The general contractor, who brought a claim against the subcontractor more that five years after August 19, 2002, argued that the statute of limitations should not have begun to run until the general contractor sent the subcontractor a letter formally rejecting the subcontractor’s work. However, Judge Kiser found no ambiguity in the flow down provision, and applied the statute of limitations to the subcontract as it was specified in the prime contract. The lesson to be learned, therefore, is that all parties to construction contracts and subcontracts in Virginia must be aware of any potential flow down provisions and must recognize that contractual provisions affecting their rights may not necessarily be found in the subcontract itself.

<< Prev     2    Next >>