Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
May/June 2009 Volume XIV  Number 3

IN VIRGINIA, FLOW DOWN PROVISIONS MAY BE USED TO ESTABLISH PROCEDURAL REQUIREMENTS RELATED TO DISPUTE RESOLUTION

Subcontracts in the construction industry commonly contain a “flow down” provision. In a typical flow down provision, the general contractor includes language that requires subcontractors to assume the same obligations and requirements toward the general contractor that the general contractor assumes toward the owner. Additionally, subcontractors are entitled to the prime contract’s dispute-resolution and redress provisions in their disputes with the general contractor. The most basic flow down provisions require that subcontracts incorporate the terms of the prime contract, the general conditions, and all other prime contract documents. Of course, flow down provisions are nearly infinitely flexible, and the owner may mandate that certain obligations in the prime contract appear in subcontracts, while permitting the general contractor to exclude other portions of the prime contract in its subcontracts.

Virginia law recognizes the construction industry practice of including “flow down” provisions in subcontracts, and permits flow down provisions to include procedural requirements governing litigation. In Steadfast Ins. Co. v. Brodie Contractors, Inc., 2008 U.S. Dist. LEXIS 88448, Judge Kiser of the U.S. District Court for the Western District of Virginia granted summary judgment for the defendant masonry subcontractor, who argued that the general contractor failed to file suit within the requisite statute of limitations. The contractor filed suit against the subcontractor a little more than five years after the substantial completion date. Accordingly, the dispositive issue was whether the substantial completion date or some other date triggered the running of Virginia’s five-year statute of limitations for breach of a written contract.

The general contractor, Skanska USA Building, Inc. (“Skanska”), entered into a prime contract with the Danville Regional Medical Center (“DRMC”) for remodeling and renovation work. The prime contract contained a provision that stated that all subcontract agreements “shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights… that the Contractor, by the Contract documents, has against the owner.” In forming a subcontract with Brodie Contractors, Inc. for masonry work, Skanska implemented the prime contract’s flow down provision by including language in the

subcontract that stated that “[t]he Contract Documents consist of this Agreement and… the Agreement between Owner and Contractor for the… Project, all Conditions to the Agreement between the Owner and Contractor (General, Supplementary and any other Conditions)....” Although Skanska could have modified Brodie’s rights with respect to Skanska, it declined to, and instead included all of the provisions of the prime contract in the subcontract.

One of the provisions of the prime contract addressed the date on which the statute of limitations would begin to run for any claims. In relevant part, the language of the prime contract stated that, with respect “to acts or failures to act occurring prior to the relevant date of substantial completion, any applicable statute of limitations shall commence to run any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of substantial completion [sic].” Despite this inelegant language, it is apparent that the statute of limitations began to run on any claims by the owner against the general contractor for claims arising from the general contractor’s pre-substantial completion acts by no later than the substantial completion date.

                         
continued on page 2

        1     Next >>