Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     3    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

"NO DAMAGES FOR DELAY" CLAUSE DOES NOT PRECLUDE
CONTRACTOR'S CLAIM FOR LOSS OF EFFICIENCY DAMAGES

Oftentimes, construction contracts include "no damages for delay" clauses which bar a contractor from recovering monetary damages caused by the owner's delays to the project. Additionally, the same contracts may include provisions which limit the contractor's remedy for project delays to an extension of time only.

In Cleveland Constr., Inc. v. Ohio Pub. Employee Retirement Sys., 2008 Ohio 1630 (Ohio Ct. App. 2008), Cleveland Construction, Inc. ("General Contractor"), an Ohio general contractor, entered into a $6.3 million interior trades contract with the Ohio Public Employees Retirement System ("Owner") to build portions of a $90 million office tower in downtown Columbus, Ohio. The parties' contract included a no damages for delay clause and a clause which limited General Contractor’s remedy for project delays to an extension of time, regardless of additional costs resulting from extended general conditions.

As work on the project advanced, Owner failed to properly schedule and manage the project. As a result, General Contractor was delayed in the prosecution of its work as Owner did not provide up-to-date project schedules and had certain trades perform work out of sequence. Consequently, General Contractor sued Owner in Ohio state court for loss of efficiency damages.

The Owner moved the court for a directed verdict and insisted that General Contractor had waived its right to collect loss of efficiency damages under the no damages for delay clause. The trial court ruled that the waiver clause was unenforceable under an Ohio law precluding a project owner from disclaiming liability for a contractor's damages if the owner caused a delay to the project. After the court rejected the motion for a directed verdict, the jury found that Owner had materially breached the contract and was liable to General Contractor for $640,000 in increased costs.

On appeal, Owner took exception to the court's interpretation of the statute. Specifically, Owner argued that General Contractor's claim was one for acceleration costs, not delay damages, and that acceleration costs were not expressly included in the Ohio statute. Thus, the Owner contended, the statute invalidating no damages for delay clauses was inapplicable and General Contractor was barred from recovering any damages, including its acceleration costs.

The Court of Appeals of Ohio, Tenth Appellate District, disagreed. Specifically, it followed the trial court's decision inasmuch as the concept of a "delay" broadly encompasses schedule

acceleration and loss of efficiency. A project owner's delay, for example, could give rise to several types of damages: inefficiency costs, acceleration costs, loss of productivity costs, extended general conditions and unabsorbed home office overhead costs. Although the Ohio statute abrogating no damages for delay clauses did not expressly include "acceleration costs," acceleration costs are intimately associated with project delays. The court found the legislature's purpose in invalidating no damages for delay clauses was to prevent owners from escaping liability when the owner caused the project delay. Liability in this context, the court held, included the natural consequences of a project delay (e.g., acceleration and inefficiency costs).

The second issue raised on appeal by Owner was whether General Contractor was precluded from recovering delay damages because General Contractor failed to request extensions of time to complete its work at the time it became apparent that the project would be delayed. In addition to the no damages for delay clause, the parties' contract included a provision which limited General Contractor's remedy for delays to time extensions only.

The trial court, relying on the Ohio statute invalidating no damages for delay clauses, held the remedy limitation clause equally unenforceable. The appellate court agreed. In its decision, the appellate court held that Ohio law clearly invalidated any contractual provision that not only waived liability for delay, but also limited any remedy for delay. Because this contract provision was unenforceable, General Contractor was not required to request time extensions. The appellate court therefore upheld General Contractor's jury award of $640,000.

As highlighted in Cleveland Construction, many construction contracts include no damages for delay clauses which either completely bar or limit the owner's liability to the contractor for project-related delays. Many states, however, including Ohio, California, Minnesota and Colorado, have either completely abrogated or severely limited the enforceability of these clauses. Accordingly, depending upon the jurisdiction, the mere presence of such a provision does not guarantee that the owner can enforce a no damages for delay clause. As Cleveland Construction indicates, the concept of a project delay generally includes damages which one would naturally expect to result from a delay (acceleration, inefficiency, etc). How a state conceptualizes or defines a "delay" will therefore determine the extent to which the no damages for delay clause is enforceable or not.

<< Prev     3    Next >>