Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
May/June 2007 Volume XVII  Number 3

CONSULTANT CANNOT TORTIOUSLY INTERFERE WITH AN
OWNER-ARCHITECT CONTRACT THAT HAS BEEN TERMINATED

An architectural consultant cannot tortiously interfere with an architect’s contract with an owner after the architect-owner contract has been terminated. This lesson is illustrated in the case of Paul Steelman Ltd. v. HKS, Inc., 2007 U.S. Dist. LEXIS 5886 (D. Nev. 2007).

In this case, the owner contracted with an architect to perform architectural services on a project involving the expansion and renovation of a Connecticut casino. Pursuant to the architectural contract, the architect was permitted to retain consultants to assist it in performing architectural services on the project. The architect entered into a consulting agreement with a consultant to provide project management, construction documentation and construction administration services on the project on behalf of the architect.

Five months after the owner entered into the contract with the architect, the owner notified the architect that it was terminating the contract for convenience. The architect subsequently notified the consultant of the termination for convenience. The architect also requested that in accordance with the parties’ consulting agreement, the consultant not communicate or deal directly with the owner. Despite the architect’s request, the consultant did communicate directly with the owner and was subsequently hired as the new project architect. As a result, the architect brought suit against the consultant on multiple counts, including tortious interference with the architect’s contract with the owner.

The architect alleged that the consultant interfered with the architectural contract by communicating directly with the owner without authorization and despite the architect’s request. The architect claimed that this communication allowed the project to proceed utilizing the architect’s design without final payment to the architect. As such, the architect argued that architectural contract’s payment obligations survived the termination of the contract.

The consultant countered that the architectural contract was terminated by the owner prior to any direct communication between the consultant and the owner. Thus, the consultant argued that the communication could not have interfered with the architectural contract.

The court ruled in favor of the consultant. The court noted that because the architectural contract was terminated for convenience by the owner before the alleged interference occurred, the architect no longer had any contractual rights which could be violated. The court observed that as a result of the termination for convenience, there was in fact no valid, existing contract with which the consultant could have interfered.

The court’s ruling in this case stands for the clear proposition that a party cannot tortiously interfere with a contract that has been previously terminated. As a result of this case, consultants should be aware that if they opt to continue on a project or to take over for an architect after a falling out between the architect and the owner, there are proper procedures to be followed. It is not proper for a consultant to interfere with an architect’s contract with an owner. However, once the contract is terminated, it may be proper for a consultant to communicate directly with the owner and ultimately take over the architect’s position after termination.



        1     Next >>