 |
 |
 |
 |
 |
 |
 |
| |
May 2000 Newsletters
Katz & Stone,
L.L.P. Construction Newsletter
May/June 2000
Volume X, Number III
FOURTH CIRCUIT HOLDS MARYLAND'S
10-YEAR STATUTE OF REPOSE APPLIES TO SUBCONTRACTORS
Statutes of repose typically provide protection
to those involved in the construction process, after a specified
time period has passed, by cutting off all claims arising from
improvements made to real property. Based on a recent Fourth
Circuit Court of Appeals decision, Maryland subcontractors may
rest assured that they will receive the same protection as general
contractors under the Maryland statute of repose. Under
the Maryland statute, claimants may not bring suit against architects,
professional engineers, or contractors more than ten years after
the improvements to real property first became available for use.
As to all other defendants, the statute provides repose twenty
years after the improvements became available for use.
In Hartford Insurance Company of the Midwest v. American Automated
Sprinkler Systems, Inc., a hotel experienced $1.6 million
in damages due to flooding when, in 1996, cold weather caused
a standpipe cap to detach and a firehose valve to crack.
The hotel management contacted the sprinkler-system subcontractor
who had installed the piping in 1982 to inform it of the situation.
The subcontractor returned to repair the system.
The insurer of the hotel subsequently brought a subrogation action
for the damages against the subcontractor. The insurer claimed
the subcontractor had improperly constructed and installed the
standpipe system in 1982. The subcontractor moved for summary
judgment arguing the Maryland ten-year statute of repose applied
and therefore barred claims brought more than ten years after
completion of the improvement to the property. The district
court granted the motion and entered judgment for the subcontractor.
The insurer appealed to the Fourth Circuit and argued that the
term "contractor" as used in the Maryland statute of
repose is not applicable to subcontractors. The insurer
argued that the term "contractor" as used by the American
Institute of Architects ("AIA") refers only to the contractor
in privity with the owner - i.e. the general contractor.
As further support for its argument that the ten-year statute
of repose did not apply to subcontractors, the insurer argued
that Maryland's mechanic's lien statute defines the terms "contractor"
and "subcontractor" differently.
The Fourth Circuit rejected the insurer's arguments and affirmed
the district court's holding. The court held the term "contractor"
as used in the statute of repose includes subcontractors.
The court reasoned this result was consistent with the intent
of the statute to protect all parties involved with the actual
construction of improvements to real property. The Fourth
Circuit also looked to definitions of the term "contractor"
in several dictionaries which further supported the proposition
that the term "contractor" includes subcontractors.
In addition, the court examined the rationale of the statute of
repose and found that the legislative motivation behind
granting heightened protection to architects, professional engineers,
and contractors was the fact that changes in Maryland's tort law
had dramatically expanded the potential for liability of parties
involved in the construction process. Thus, the court reasoned
that the purpose of the statute could only be served by providing
the heightened protection to subcontractors.
As the Hartford Insurance case illustrates,
statutes of repose provide important protection against claims
which surface well after the contractor's work has been completed.
As statutes of repose differ from state to state (e.g., Virginia's
is only five years), contractors, subcontractors and their insurers
would be well-advised to consult their legal counsel whenever
construction-related claims are asserted years after construction
has ended.

ILLINOIS' HIGHEST COURT UPHOLDS
THE RIGHT OF AN INSURED TO CHOOSE WHICH GENERAL LIABILITY INSURER
MUST DEFEND A CLAIM
When a general contractor has been named as an
additional insured to a subcontractor's general liability
insurance policy, the general contractor's intent is that the
subcontractor's policy cover any claim falling within its scope,
without involving the general contractor's own policy. In
an attempt to effectuate this intent, general contractors will
endeavor to have the subcontractor's insurer provide a defense
while at the same time notifying their own insurer that they do
not intend to seek that insurer's coverage. In the insurance
industry, this practice is known as a 'targeted tender.'
In John Burns Construction Company v. Indiana Insurance Company,
the Illinois Supreme Court recently addressed in an unpublished
opinion whether an insured can choose which general liability
insurer would defend a claim when the insurance policy invoked
by the insured contains an 'other insurance' clause. 'Other
insurance' clauses typically provide that, if other primary insurance
is available to an insured for a loss, each insurer will cover
the loss in equal shares. Affirming that an insured has
the right to choose which of several available insurers must defend
a particular claim, the court clearly stated that the 'other insurance'
clause in an insured's policy does not supersede the insured's
right to tender defense of a claim to one insurer alone.
In John Burns, John Burns Construction Company, the general
contractor, entered into a subcontract with Sal Barba Asphalt
Paving, a paving subcontractor, to pave a parking lot at a commuter
railroad station. As required by the subcontract, the subcontractor
added the general contractor to its liability insurance policy
as an additional insured. After the paving had been completed,
a person using the rail station slipped and fell in the parking
lot the subcontractor had paved, and subsequently sued the general
contractor for his injuries.
The general contractor requested that the subcontractor's insurer
defend and indemnify it against the claim and indicated that it
looked solely to the subcontractor's insurer for its defense.
The general contractor further indicated that it did not want
its own liability insurer to become involved in the suit.
The subcontractor's insurer initially refused to defend the general
contractor. After the general contractor instituted suit
against the subcontractor's insurer for its failure to defend,
the subcontractor's insurer changed its tune, taking the position
that although it had a duty to defend, the general contractor's
insurer was required to share equally in the defense by virtue
of the 'other insurance' clause in its policy. The other
insurance clause provided that, if other primary insurance was
available to the general contractor for a loss, each insurer would
cover the loss in equal shares. The subcontractor's insurer
prevailed in two lower Illinois courts and the case was subsequently
appealed to the Illinois Supreme Court.
The Illinois Supreme Court reversed the two lower courts, holding
that the general contractor, as the insured, had the right to
choose which of its insurers would be required to defend and indemnify
it and that the 'other insurance' clause did not limit the general
contractor's right to select which insurer was required to cover
the claim. The court based its decision on the notion that
an insured may knowingly forego an insurer's involvement by instructing
the insurer not to involve itself in the litigation.
The court held that the 'other insurance' clause in the general
contractor's policy did not overcome the general contractor's
right to select which insurer would be required to defend the
claim. Citing several previous cases, the court noted that
'other insurance' clauses only come into play as a method of apportioning
coverage expenses among several insurers when the insured has
in fact triggered coverage from several insurers. According
to the Illinois Supreme Court, the presence of such clauses does
not, in itself, automatically trigger the coverage of all available
insurers when the insured has purposefully chosen to restrict
tender of a claim to a single insurer.
As the court's decision in John Burns illustrates, the
validity an insured's right to make a 'targeted tender' of claims
to an insurer or insurers of its choice continues to be upheld.
The mere presence of an 'other insurance' clause does not allow
the targeted insurer to seek contribution from an insurer whose
coverage the insured has purposefully declined to invoke.
PENNSYLVANIA COURT HOLDS GENERAL
CONTRACTOR DIRECTLY LIABLE TO MATERIAL SUPPLIER PURSUANT TO JOINT
CHECK AGREEMENT
Contractors often use joint check arrangements
as a means of inducing suppliers to furnish materials to a financially
weak or unproven subcontractor. Contractors utilizing this
practice need to take special care to avoid incurring direct liability
to suppliers.
In Glen-Gery Corp. v. Warfel Constr. Co., 734 A.2d 926;
1999 PA Super 175 (1999), a Pennsylvania appeals court considered
the question of whether a general contractor is directly liable
to a material supplier under a joint check agreement even if the
amount owed the supplier would exceed the subcontract price.
Glen-Gery involved the construction of the Nitrauer Elementary
School ('school project' or 'project') in Lancaster, Pennsylvania.
The Warfel Construction Company ('general contractor') was the
general contractor on the project and accepted Lawver Masonry's
('subcontractor') $741,000 bid to be the unit masonry and architectural
precast subcontractor on the project. The subcontractor
in turn utilized Glen-Gery Corporation ('masonry supplier') as
its supplier of block and other specialized masonry products for
the project.
Shortly after signing the subcontract and purchase order, the
subcontractor met with the general contractor and acknowledged
that it was 'broke.' As a result, the subcontractor requested
that the general contractor pay for materials and the subcontractor's
labor expenses on a weekly basis. Upon hearing of the subcontractor's
financial troubles, the masonry supplier requested that the general
contractor execute a joint check agreement.
Under the proposed joint check agreement (which the masonry supplier
prepared) the general contractor agreed to issue joint checks
(payable to subcontractor and masonry supplier) to cover the cost
of 'all materials purchased by [subcontractor] for incorporation
to [the school project].' The agreement essentially provided
that the masonry supplier would supply the subcontractor with
materials on credit and would be compensated by the general contractor
via joint check for all amounts reflected on the masonry supplier's
invoices.
Shortly after the parties executed the joint check agreement,
the subcontractor filed for bankruptcy and the general contractor
began issuing the subcontractor and its masonry supplier joint
checks. Almost six months into the project, however, the
general contractor met with the subcontractor to discuss the payment
status of the subcontract. The general contractor informed
its subcontractor that the subcontractor had exceeded the $741,000
subcontract amount and would not be paid any more money.
As a result of this development, the subcontractor stopped working
on the project and sent the general contractor a termination notice.
The general contractor then requested that the subcontractor supply
it with information indicating outstanding amounts due and owing
the subcontractor's suppliers. Because the general contractor
had already paid more than the subcontract amount, the general
contractor refused to pay $62,000 in masonry supplier invoices.
The general contractor further questioned whether the materials
invoiced were actually used on the project.
At trial, the court entered a verdict in favor of the general
contractor. The trial court held that because the masonry
supplier authored the joint check agreement, it would construe
that agreement against the supplier. Moreover, the trial
court indicated that the agreement was merely a payment mechanism
that did not bind the general contractor to pay more money to
the masonry supplier than it owed the subcontractor under its
$741,000 subcontract.
On appeal, the Pennsylvania Superior Court reversed and remanded
the trial court's decision. The appellate court noted
that '[t]he parties' joint payee check agreement was a measure
purposefully intended to create additional security for a materials
supplier of a soon-to-be-bankrupt/insolvent subcontractor,' and
determined that under the agreement the general contractor clearly
and unambiguously had agreed to pay the masonry supplier for 'all
materials' the masonry supplier provided the subcontractor for
use in the school project. The Superior Court then remanded
the case for the trial court to determine (1) whether the material
indicated in the invoices was purchased by the subcontractor;
and (2) whether the subcontractor purchased the material for incorporation
into the school project. The court ordered that if both
questions were answered in the affirmative, the masonry supplier
was entitled to a judgment for the unpaid invoices plus accrued
interest. Alternatively, the court ordered that verdict
be entered for the general contractor if the trial court determined
that the materials invoiced were not supplied to the subcontractor
for use in the school project.
The Glen-Gery case illustrates that contractors should
not assume that a document entitled 'joint check agreement' is
a mere payment mechanism which does not create direct liability
to the supplier or jeopardizes a favorable subcontract price.
Instead, contractors should carefully scrutinize all joint check
agreements drafted by others, or better yet, prepare and utilize
their own form agreement.
NEW YORK COURT HOLDS SURETY
CANNOT ESCAPE OBLIGATIONS UNDER 'PAY-WHEN-PAID' CLAUSE
Construction contracts between general contractors
and subcontractors often contain provisions commonly referred
to as 'pay-when-paid' clauses. A 'pay-when-paid' clause
attempts to limit the general contractor's liability for payments
to subcontractors in situations where the owner defaults and fails
to pay the general contractor for amounts otherwise due the subcontractor.
These clauses have been the subject of many judicial decisions
in recent years and in Blandford Land Clearing Corp., et al.
v. National Union Fire Ins. Co., 698 N.Y.S.2d 237 (1999),
the New York Court of Appeals considered a surety's attempt to
rely on the equivalent of a 'pay-when-paid' clause contained in
the subcontract as a defense to a subcontractor's claim on the
bond.
In Blanford Land Clearing Corp., the general contractor
and the owner entered into a contract for the construction of
a shopping center in Bronx, New York. The owner defaulted
and refused to pay the general contractor. At the time of
the default, the subcontractor was owed approximately $500,000
for work performed on the project. Because the general contractor
had not yet received payment for the subcontractor's work, the
general contractor refused to pay the subcontractor by relying
upon the terms of the subcontract which expressly stated that
for payment purposes, the general contractor is acting as 'agent
of owner' and that payment from the owner to the general contractor
was a condition precedent to the subcontractor receiving payment.
The subcontractor filed suit against the general contractor's
payment bond surety. In response, the surety argued that
the terms of the subcontract, which were incorporated into the
terms of the payment bond, extinguished any obligation the surety
had to pay the subcontractor until the owner made payment to the
general contractor. The surety's motion to dismiss the subcontractor's
claim on this basis was granted by the trial court.
The subcontractor appealed, contending that the surety could not
evade its obligation to pay the subcontractor under the payment
bond and the 'agent of owner' provision was merely a thinly disguised
'pay-when-paid' clause that was void against public policy and
unenforceable pursuant to New York state law. In response,
the surety argued that its obligation to pay the subcontractor
was coextensive with that of the general contractor and, absent
payment from the owner to the general contractor, it had no obligation
to satisfy the subcontractor's claim.
The Court of Appeals rejected the surety's argument and held in
favor of the subcontractor. The court began its analysis
by recognizing that the surety's payment bond represented an 'unqualified
promise' to make payment to any 'claimant,' i.e., subcontractor,
that had entered into a direct contract with the general contractor.
According to the court, the only manner in which this obligation
could be removed was if the general 'contractor promptly makes
payment, directly or indirectly, for all sums due.' Thus,
the court expressly rejected the surety's attempt to narrow its
obligation under the bond and held that the bond imposes a broader
obligation upon the surety than the subcontract does upon the
general contractor. The court further stated that if the
surety wanted to limit its obligation to pay the subcontractor
to that of the general contractor, it could have modified the
terms of the bond. Absent such language, the court held
that the bond's unconditional promise to 'pay for labor, materials
and equipment furnished for use in performance of the construction
contract' required the surety to pay the subcontractor the amount
due and owing.
The court further rejected the surety's attempt to rely on the
'agent of owner' language of the subcontract as a basis to deny
payment by holding that to enforce such a provision would violate
established contract principles. Additionally, the court
stated that such a clause would not be effective to release the
general contractor, and therefore the surety, from its contractual
obligation to the subcontractor, as the general contractor's attempt
to label itself as the 'agent of owner' for payment purposes would
offend public policy and could not be enforced.
The court's decision in Blanford Land Clearing Corp. demonstrates
the judiciary's general reluctance to allow sureties to rely on
pay-when-paid clauses as a defense to payment bond claims.
Given that New York state law renders pay-when-paid clauses void
against public policy, there is probably little the surety could
have done to avoid the result in this case. Nevertheless,
sureties in states where pay-if-paid clauses are enforceable would
be well-advised to modify payment bond language to clearly and
expressly make their obligations co-extensive with that of the
general contractor, and subcontractors must be aware of the potential
effect.
|
|
 |
 |
 |
|