March/April 2003 Newsletters

 

Katz & Stone, L.L.P. Construction Newsletter
March/ April 2003

 

VIRGINIA COURT HOLDS THAT AIA SUBCONTRACT’S ARBITRATION PROVISION DOES NOT PRECLUDE LITIGATION OF MILLER ACT CLAIM


Contractors familiar with the American Institute of Architect’s (“AIA”) series of form contracts are likely aware that they call for arbitration, rather than litigation, of claims arising out of or related to the contract. Many contractors who use AIA forms may therefore presume that any payment bond or mechanic’s lien claim they may have is also subject to arbitration. As illustrated by a recent decision of the United States District Court for the Eastern District of Virginia, for contractors using the 1987 edition of the AIA subcontract, however, such an assumption would be a mistake.

In the case of
United States ex rel. American Sheet Metal Corp. v. The Travelers Ins. Co., 222 F.Supp.2d 789 (E.D. Va. 2002), a contractor entered into a construction contract with the Navy to repair a roof. In accordance with the requirements of the federal Miller Act, the contractor’s surety issued a payment bond guaranteeing payment of all claims for labor and materials. Subsequently, the contractor entered into a subcontract for certain sheet metal work on the project.

After the contractor failed to timely pay the subcontractor’s requisitions, the subcontractor brought suit against the contractor and its surety seeking recovery of its money through its claim against the Miller Act payment bond. Hoping to avoid litigation of the subcontractor’s claim in federal court, the contractor sought a stay of the action and a ruling directing the parties to arbitrate pursuant to an arbitration provision in the subcontract. The subcontractor argued that arbitration was inappropriate because the subcontract’s arbitration clause excluded Miller Act claims.

The subcontract between the parties was the 1987 edition of the AIA Standard Form of Agreement Between Contractor and Subcontractor (A401). In resolving the parties’ dispute over arbitration, the court had to reconcile two separate sections in the subcontract. Section 6.1 provided that any “controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract ... shall be settled by arbitration.” At the same time, Section 6.5 provided that all provisions, including Section 6.1, “shall not be deemed a limitation of rights or remedies which the Subcontractor may have under Federal law, under state mechanics’ lien laws, or under applicable labor and material payment bonds unless such rights or remedies are expressly waived by the Subcontractor.” Recognizing that the Miller Act gives the subcontractor the right to sue on the bond in federal court, the court concluded that Section 6.5 specifically excluded from arbitration such claims and that the subcontractor had not expressly waived its right to bring such claims in court.

The court’s decision in
American Sheet Metal is a poignant reminder to contractors still using the 1987 edition of A401 that its form arbitration provisions, in fact, do not require arbitration of all disputes relating to the subcontract. Based on the court’s reasoning and the language in Section 6.5, subcontractors still have the right to pursue their Miller Act, mechanic’s lien and private-project bond claims in court without waiting for the resolution of related claims by arbitration. Contractors wishing to avoid this result and better ensure that such claims are stayed pending the results of an arbitration should either delete the exclusion language of Section 6.5 or use the 1997 edition of A401, which does not include such exclusory language. Contractors should also void blind reliance upon an arbitration provision without consideration of the contract’s other terms. Other contract provisions must be reviewed to ensure they do not limit the agreement to reduce disputes through arbitration.

 

REVISIONS TO THE DISTRICT OF COLUMBIA’S MECHANIC’S LIEN STATUTE CREATE MORE HOOPS FOR CONTRACTORS TO JUMP THROUGH

Contractors furnishing labor and/or material to a construction project assume that, so long as they have not signed a document waiving their mechanic’s lien rights, they will have little problem filing a mechanic’s lien under the law of the state where the project is located. While such an assumption may suffice on most occasions and in many jurisdictions, amendments enacted last year to the District of Columbia’s mechanic’s lien statute have erected several potentially new obstacles to the filing a mechanic’s lien.

The most significant change to the District’s mechanic’s lien statute relate to the requirements for establishing a lien. Mechanic’s liens in the District are established by the filing of a notice of intention to hold a lien on the improved property. While a mechanic’s lien is still established by the filing of the requisite notice, current law has imposed new requirements on what must be filed with such notice. Specifically, the mechanic’s lien statute now requires that a notice of lien “shall include” (1) a copy of the work agreement signed by all parties; (2) a valid residential home improvement contractor’s license issued by the D.C. Department of Consumer and Regulatory Affairs (“DCRA”); (3) a certificate of good standing issued by the DCRA; and (4) a certificate or statement of good standing from the D.C. Office of Tax and Revenue (“OTR”).

Due to the present wording of the mechanic’s lien statute, the requirement to include a copy of a signed work agreement and a valid residential home improvement license is troubling. Although the statute does not expressly state that such documents must be attached only “if applicable,” it would seem to be a matter of common sense that a contractor working on a commercial project would not need to furnish proof of a home improvement license to file a lien. Similarly, as the mechanic’s lien statute does not expressly limit lien rights to those persons having a signed, written contract, there is good reason to argue that the requirement to include a signed agreement would not apply when such a document does not exist. Nevertheless, as no court has yet to address the proper interpretation of these provisions, the statute’s unqualified requirement that a notice “shall include” such documents causes some uncertainty as to whether a contractor without a home improvement license or without a work agreement signed by both parties will be permitted to file a lien. In light of the statute’s ambiguity, the best practice for a contractor to follow is to always obtain written authorization for work signed by the party for whom such work is performed and, if it has a home improvement license, to attach that license to its notice or adequately describe the work in the notice to clarify that it is not a home improvement project.

The requirement to include certificates of good standing from the DCRA and the OTR should also be noted. The statute requires a lien claimant to file its notice within 90 days after completion of an improvement or its lien rights are lost. If a contractor is running up against this deadline, the requirement to obtain such certificates can significantly slow its ability to timely file a lien. For example, in order to obtain a certificate from DCRA, a contractor must be registered to do business in the District. A contractor who has performed work in the District without having registered must first register and then apply for a certificate of good standing prior to filing a lien. Even on an accelerated schedule, this process can take several days to accomplish. For more details regarding how to obtain such certificates, contractors may call DCRA’s Call Center at (202) 442-4400 or the OTR’s Customer Service Center at (202) 727-4829.

Contractors must also be aware that the time to file suit to enforce a lien has also been amended. In the past, lien claimants were permitted to commence suit within a year after the filing of their notice or within 6 months from the completion of the building. Under current law, lien claimants must commence an action to enforce a mechanic’s lien within 180 days after the filing of a notice of intent to hold a lien or from the date of completion of the building. Thus, under current law, the time in which to file suit has been narrowed.

Contractors should be aware that the process to file a mechanic’s lien in the District is now more treacherous than it once was. Thus, it is more important than ever before for contractors performing work on private projects in the District to know the requirements of the statute and do what is necessary, in advance of a payment dispute, to ensure that they will be able to timely assert a mechanic’s lien on the project.

 

MARYLAND COURT ENDORSES USE OF EICHLEAY FORMULA
TO QUANTIFY CLAIMS FOR EXTENDED HOME OFFICE OVERHEAD

The method for calculating a claim for extended home office overhead due to delay that is most widely accepted by federal and state courts is the “Eichleay” formula. Prior to last year, however, Maryland courts had hardly discussed, much less formally approved, the method. In Gladwynne Construction Company v. Mayor and City Council of Baltimore, 147 Md. App. 149, 807 A.2d 1141 (2002), however, the second highest court in Maryland appears to have endorsed its use.

In
Gladwynne, a general contractor was obligated to renovate a Baltimore City high school within a contract time of 180 calendar days. Completion of the renovation work was delayed approximately 300 days. The delays primarily arose from the contract’s requirement that the contractor replace utility lines located in a crawlspace, which neither the contractor nor the city was ever able to locate. Eventually, the contractor had to drastically alter its method for such work. Moreover, delays were also caused by the architect, who continued to make numerous changes in the work late into the project. The contractor filed suit to recover its extended home office overhead costs, which it calculated using the Eichleay formula. While the city conceded that there were some delays in the early stages of the project for which the contractor was not responsible, it disagreed with the delay period claimed by the contractor. The lower court established the delay period and awarded the contractor certain damages. However, the court did not award damages for extended home office overhead costs because it concluded that all of the elements of the Eichleay formula had not been met.

On appeal, the lower court’s decision was reversed. Finding no Maryland case law which expressly adopted the Eichleay formula, the appellate court noted that it is the most widely approved formula for calculating unabsorbed overhead costs arising out of government-caused delay. (See below). In fact, the court noted that in some jurisdictions the Eichleay formula is the only accepted method of calculating unabsorbed home office overhead.

The court stated, however, that, in order for a contractor to recover under the Eichleay formula, it must prove three things: (1) the contract was suspended, delayed, or disrupted by the government; (2) the contractor was forced to “stand by” during the delay; and (3) while “standing by” during the suspension, delay, or disruption, the contractor was unable to take on other work. Should the contractor be able to establish a
prima facie case of entitlement to use the formula, the government, in order to defeat the claim, must demonstrate that the contractor did not suffer any loss either because it was able to reduce its overhead or because it was able to take on other work during the delay.

The court clarified that “standby” does not require that the contractor's workforce be idle or that work on the project be entirely suspended. Rather, a contractor may be deemed unable to take on additional work if the owner causes a delay of uncertain duration or if the contractor's bonding capacity is limited. The appellate court then concluded that the contractor had been put on standby by the city’s delays because the contractor could not know when the city would complete the redesign process and had to remain ready to perform changed and additional work until the final change order was issued. Moreover, the court determined from the contractor’s testimony before the lower court that its limited bonding capacity had also prevented it from taking on additional work during the delay.

Therefore, the appellate court concluded that the contractor appeared to have presented sufficient evidence to satisfy the Eichleay formula for at least some portion of the total delay. Because, in refusing to award any delay damages for overhead expenses, the lower court had failed to identify which element of the formula was not satisfied, the appellate court vacated the lower court’s judgment and remanded the case for it to reconsider whether the Eichleay formula was satisfied and, if so, for what period of time and at what daily rate.

While the Maryland Court of Special Appeals did not go as far as saying the Eichleay was the exclusive measure of claiming extended home office overhead, its decision in
Gladwynne clearly approves of Eichleay and sets out the elements that are prerequisites to its use. Contractors able to demonstrate the elements of an extended home office overhead claim will now have a proven method of calculating the amount of their claims under Maryland law.

The Eichleay Formula can be summarized as follows:

1.

Contract billings on the project        
--------------------------------------
X
Total overhead for
the contract period
=
Overhead allocable
to the contract
Total billings during the
contract period
       


2.

Overhead allocable to the contract    
--------------------------------------
=
Daily contract overhead amount
Number of days in ordinal contract period    


3.

Daily contract overhead amount
X
Number of days of delay
=
Recoverable extended home office overhead

 

FEDERAL CIRCUIT HOLDS THAT DISCLAIMER ON SPECIFICATIONS DOES NOT SHIFT RISK OF DESIGN DEFECTS TO THE GENERAL CONTRACTOR

In White v. Edsall Construction Co., Inc., 296 F.3d 1081 (Fed. Cir. 2002), the U.S. Court of Appeals for the Federal Circuit affirmed that if the government provides design specification to a general contractor, a general disclaimer on those specifications which requires the contractor to check and verify the plans will not shift the risk of design flaws to the contractor. Although the contractor has a duty to investigate or inquire about obvious ambiguities, inconsistencies, or mistakes, it does not have to ferret out hidden or subtle errors in the specifications. This decision affirms that a disclaimer on design specifications should not make a contractor a guarantor of those specifications.

Edsall arose out of the U.S. Army’s (“owner”) awarding Edsall Construction (“contractor”) a fixed-price contract for the construction of a facility to house the Montana National Guard's helicopters. The facility included two hangars the owner’s engineers had designed. The specification and drawings called for "tilt-up canopy doors" weighing about 21,000 pounds each. The design used a complex system of motors, cables, pulleys, and counterweights to open the doors. The drawings showed cables attaching to the doors at three points called "pick points." The cables ran from the pick points up over a main truss, over several sets of pulleys and then down to the counterweights.

The drawings also contained a disclaimer that the canopy “DOOR DETAILS, ARRANGEMENTS, LOADS, ATTACHMENTS, SUPPORTS, BRACKETS, HARDWARE ETC. MUST BE VERIFIED BY THE CONTRACTOR PRIOR TO BIDDING.” The engineer testified that he added the disclaimer as an "informational flag" that bidders should verify the three-pick-point design.
The contractor subcontracted the canopy door construction to a subcontractor with substantial experience in designing and building hangar doors. The subcontractor’s owner testified that he read the disclaimer as a "heads up that there may be problems" but that his review of the drawings showed nothing "obviously wrong." After beginning construction, though, the subcontractor discovered that the three-pick-point design would not work and suggested an alternate design.

By the time the owner approved the new design, however, the steel trusses for the doors had been fabricated and delivered to the site. This required the subcontractor to field modify the trusses. After the subcontractor had calculated its costs related to the extra work, the contractor submitted a $70,000.00 extra work claim to the owner. The owner rejected the claim, stating that the subcontractor had not complied with the disclaimer and verified the information prior to bidding.

The Board of Contract Appeals found that the owner’s specifications contained defects and held that (1) the contractor’s pre-bid review of the specifications was reasonable and (2) the disclaimer did not shift the risk of design inadequacies to the contractor. On appeal, the Court of Appeals affirmed.

The court cited the
Spearin doctrine tenant that when the government provides, and requires its general contractor to follow, design specifications, the government impliedly warrants those specifications. The court thus rejected the owner’s argument that the general disclaimer required the contractor to “verify” the plans and shifted the risk of design defects to the contractor. The court agreed that the disclaimer did require the contractor to verify basic details, but found that the disclaimer did not clearly alert the contractor that the design may contain substantive flaws requiring correction and approval before bidding. Absent an “express and specific” disclaimer, the contractor was entitled to rely on the specifications and to recover any additional costs it reasonably incurred to remedy the defects.

Although the risk of design defects
can be passed through to contractors, Edsall illustrates that the Spearin doctrine is alive and well. Absent an express shifting of the risk of faulty design specifications, contractors who must follow an owner’s design do not guarantee the adequacy of that design.