 |
 |
 |
 |
 |
 |
 |
| |
March 2000 Newsletters
Katz & Stone,
L.L.P. Construction Newsletter
March/April 2000
Volume X, Number II
SURETY'S FAILURE TO NOTIFY GOVERNMENT
BARS CLAIM
Although the payment and performance bonds required
by the Miller Act are intended to protect the government from
a general contractor's default, it is well-recognized that the
government owes a duty to the general contractor's surety once
it is aware of the general contractor's default. The courts
have labeled the surety's right to recover against the government
for a breach of this duty, the right to 'equitable subrogation.'
In Hartford Fire Ins. Co. v. United States, 1999 U.S. App.
Lexis 3197 (Fed. Cir. 1999), a federal court of appeals demonstrated
the narrow scope of this remedy.
The dispute in Hartford Fire arose out of a contract between
the United States ('the government') and a Section 8(a) general
contractor for the construction of a Criminal Investigation Division
Field Operations Center at Fort Leonard Wood, Missouri (the 'Project').
The general contractor subsequently subcontracted various administrative
tasks for the Project to a subcontractor which included obtaining
surety bonds for the Project. The general contractor and
subcontractor jointly applied for and received surety bonds from
the Hartford Fire Insurance Company (the 'surety').
As the Project neared completion, the subcontractor advised the
government that the general contractor had failed to deposit the
last two progress payments in the proper account and that, as
a result, the Project's subcontractors and suppliers were in danger
of not getting paid. Four days later, the subcontractor
further notified the government that the general contractor had
made unauthorized withdrawals from the Project account and requested
the government's intervention to ensure that the Project's subcontractors
and suppliers were paid. Despite the subcontractor's warnings
of the misappropriation of progress payments, the government subsequently
conducted a final inspection of the Project and made final payment
directly to the general contractor. Three weeks after the
general contractor received its final payment, the surety notified
the government of the numerous payment bond claims which had been
made.
The surety subsequently paid the amounts due the Project's subcontractors
and suppliers and filed an action against the government under
the doctrine of equitable subrogation. Specifically, the
surety alleged that the government had abused its discretion and
acted unreasonably to the surety's detriment by failing to take
reasonable steps in its power to ensure that payments to the general
contractor were used to pay subcontractors and suppliers.
In response, the government filed a preliminary motion to dismiss
alleging that the surety's failure to notify the government of
the general contractor's default prior to payment barred its equitable
subrogation claim. The trial court granted the government's
motion.
On appeal, the court expressly recognized that under the doctrine
of equitable subrogation, the surety could maintain a claim against
the government if the government breached its duty to act with
'reasoned discretion' toward the surety. However, the court
held that the government's equitable duty arises only upon the
surety's notification to the government that the contractor is
in default. In the present case, the court held that the
subcontractor's notice to the government of the general contractor's
impending default was insufficient to satisfy the requirement
of notice from the surety and therefore barred the surety's claims.
The court's decision in Hartford Fire has important implications
on sureties and the way they oversee bonded projects. Sureties
cannot afford to wait until bond claims are filed to put the government
on notice of a contractor's impending default. Instead,
and to ensure their rights are preserved, sureties will need to
more actively oversee bonded projects and directly notify the
government at the earliest signs of a potential default.

IDAHO SUPREME COURT LIMITS CATEGORIES
OF MECHANIC'S LIEN CLAIMANTS
In Great Plains Equipment, Inc. v. Michetti
Pipe Stringing, et al., 979 P.2d 627, 132 Idaho 754 (1999),
the Idaho Supreme Court overturned, in large part, a $3 million
judgment in favor of sixteen lien claimants under Idaho's mechanic's
lien statute against the Northwest Pipeline Corporation ('owner').
In Great Plains, the owner and Great Plains Pipeline Construction
Company ('contractor') entered into a construction contract in
which the contractor was to build 378 miles of new gas pipeline
and related facilities (compressor stations, communication sites,
etc.) between Pocatello and Burley, Idaho. From the beginning,
the project was plagued by delays in starting, extreme weather
conditions, and project cost underestimations. Eventually,
the contractor abandoned the job, leaving numerous subcontractors,
equipment lessors, insurance providers, and other vendors unpaid.
The contractor was ultimately forced into involuntary bankruptcy
and the subcontractors filed mechanic's liens against the owner
for the unpaid amounts.
At trial, the district court entered judgment in favor of the
sixteen lien claimants. On appeal, the owner challenged
numerous elements of the district court decision including, most
importantly, whether costs for: (a) leased equipment; (b) unpaid
insurance premiums; and (c) fuel and oil charges can be recovered
under Idaho's mechanic's lien statute. Under Idaho's lien
law, 'Every person performing labor upon, or furnishing materials
to be used . . . in connection with any land or building development
or improvement . . . has a lien upon the same for the work
or labor done or professional services or materials furnished.'
The Idaho Supreme Court ultimately concluded that the district
court had erroneously awarded such costs under the statute.
In reversing the lower court, the Idaho Supreme Court stated that
the operative phrase in the mechanic's lien statute required that
materials were 'to be used in' the construction. The court
noted that the 'right of lien is based on the theory that the
claimant has . . . contributed to the construction to improvement
of the property against which the lien is asserted'. Accordingly,
the court concluded 'where the labor is not used or the materials
are not incorporated into the building, structure or improvement,
no lien on land or building results.'
In reaching its decision, the court analogized the use of leased
equipment to the use of tools. Under Idaho law, costs for
tools which are not used and consumed in the construction
of the work cannot be included in a lien. Similarly, the
court reasoned that since the leased equipment was neither incorporated
into, consumed or destroyed by the construction, the leased equipment
could not be considered 'materials' under the lien law.
Accordingly, the lien claimants could not recover under the mechanic's
lien statute for unpaid rental charges or the 'use' value of the
leased equipment.
The court next turned to the question of whether
the mechanic's lien statute applied to the recovery of unpaid
insurance premiums. While the district court concluded that
a portion of each insurance contract was 'consumed' during the
pipeline construction and thus properly lienable, the Idaho Supreme
Court disagreed. The court held that liability insurance
is neither labor nor materials consumed in the process of improving
real property. While the court acknowledged that the cost
of worker's compensation insurance is recognized as 'labor' under
the mechanic's lien statute, the court refused to extend the law
to any other form of insurance. Thus, the court held parties
seeking to recover insurance costs could not recover these costs
under the mechanic's lien statute.
Finally, the court held that a supplier of fuel and lubrication
products was not entitled to recover under the statute for fuel
and oil supplied to the project. While the district court
reasoned that such charges were proper since the fuel and oil
were materials 'used and consumed' in the construction, the Supreme
Court once again disagreed. In reaching this conclusion
the court relied on previous decisions where the court held that
although costs for gasoline and oil supplied in highway construction
were recoverable under Idaho's public contractor's bond statute,
similar claims were not recoverable under the mechanic's lien
statute because such were not 'labor or materials that are lienable
under the mechanic's lien law in its relation to private structures.'
The Idaho Supreme Court ultimately reversed all lien claims against
the owner. By doing so, the court demonstrated that it would
strictly interpret the mechanic's lien statute and deny recovery
for any costs which are not clearly labor or materials consumed
in the construction process. The Idaho decision illustrates
the important principle that not every cost incurred in construction
can be recovered through a mechanic's lien. While the decision
in Great Plains was based only on Idaho's statute, given
the differences in mechanic's lien law state-by-state, contractors
need to be aware of the recoverable costs prior to asserting a
mechanic's lien.
CGL INSURER HAS DUTY TO DEFEND
UNSUITABLE FILL CLAIM
Contractors are not always aware that routine
defective construction claims may be covered under their commercial
general liability policies. In Federated Mutual Ins.
Co. v. Grapevine Excavation Inc., 1999 U.S. App. Lexis 31223
(5th Cir. 1999), a subcontractor performed excavation, backfilling
and compacting work in connection with the construction of a parking
lot for Wal-Mart in Burleson, Texas. After completion of
the lot, the owner discovered that the select fill used by the
subcontractor did not meet specifications and had caused damage
to the parking lot's asphalt surface. As a result, the owner
refused to pay the general contractor, and the general contractor
in turn brought suit against the subcontractor for damages.
The subcontractor requested a defense from its insurers and one
of the insurers refused to defend the subcontractor against the
lawsuit. In an ensuing declaratory judgment action to determine
coverage, the insurer argued that the subcontractor's use of improper
fill was an 'intentional act' and thus was not an 'occurrence'
under the policy. The district court agreed and the subcontractor
appealed.
The United States Fifth Circuit Court of Appeals reversed.
While the court recognized that according to Texas law, which
governed this case, intentional and voluntary acts are not deemed
to be an 'occurrence,' negligent acts can be considered an 'occurrence'
if the resulting damages were unforeseen or unexpected by the
insured. In the construction context, damages have been
held to be unforeseen if the contractor's defective work resulted
in harm to a third-party's work.
Using this rationale, the Fifth Circuit found the allegations
against the subcontractor were an 'occurrence' under the policy.
First, the court noted there were
no allegations that the subcontractor intentionally
used substandard materials for filling the lot. Second,
the subcontractor's use of the wrong fill damaged the work of
the paving subcontractor and, therefore, these damages could be
deemed to be unforeseen.
The Fifth Circuit also rejected the insurer's argument that coverage
was barred by the 'contractual liability' and 'impaired property'
exclusions. The contractual liability exclusion bars coverage
when the allegations against the contractor result solely from
an agreement to assume the liability of a third-party. In
this case, the allegations against the subcontractor included
both contractual indemnification and negligence. Because
the complaint alleged negligence, and not solely indemnification,
the contractual liability exclusion was held not to apply.
The court also rejected the insurer's assertion of the impaired
property exclusion which bars coverage in situations where the
damaged property can be restored merely by 'either repair, replacement,
adjustment, or removal of the work' by the contractor or by fulfilling
the terms of the agreement. In this case, the court held
the exclusion did not apply because the damage to the paving subcontractor's
work could not be restored by correcting the inadequacies of the
fill.
The Federated Mutual case illustrates the general principle
that defective construction work which damages another trade's
work may be covered under the contractor's commercial general
liability policy. While such policies generally do not cover
the cost of repairing the insured's defective work, when the work
of other trades is damaged, the policies often must respond.
MARYLAND COURT CLARIFIES 15%
RULE FOR LIEN ON RENOVATION WORK
Section 9-102(a) of the Code of Maryland was
recently revised to allow contractors to establish liens on any
building repaired, rebuilt or improved to the extent of 15% of its
value. Formerly, the threshold was 25%. In the case
of O-Porto Construction Co. v. Devon/Lanham, L.L.C., 129
Md. App. 301 (1999), the Maryland Court of Special Appeals addressed
the question of whether a particular subcontractor whose own work
did not equal or exceed 15% of a building's value could still establish
a lien on the building when the total value of all renovations exceeded
the 15% threshold. After examining prior caselaw and
the extensive legislative history of Section 9-102(a), the court
clarified that any contractor working on a property that has been
repaired or improved to the extent of 15% of its value is entitled
to a lien, regardless of the value of the individual contractor's
work.
In 1998, O-Porto Construction Company ('the contractor') filed a
complaint in the Circuit Court for Prince George's County, seeking
to establish a lien on a commercial property for unpaid concrete
work. The contractor's work represented a small portion of
a property-wide renovation undertaken by the owner, Devon/Lanham,
L.L.C. ('the owner'). After purchasing the property for $2,600,000.00,
the owner had spent $2,694,581.00 in renovations. As a result,
the owner acknowledged that the total cost of all renovations exceeded
15% of the property's value but argued that, because the contractor's
work alone did not exceed that threshold, no lien could be established
under Section 9-102(a). The Circuit Court agreed with the
owner and dismissed the contractor's complaint, taking the position
that the 15% threshold of Section 9-102(a) had not been met and,
therefore, the contractor had no right to establish a lien on the
property. The contractor appealed to the Court of Special
Appeals.
On appeal, the owner relied on a previous decision of the appellate
court, Westpointe Plaza II Ltd. Partnership v. Kalkreuth Roofing
& Sheet Metal, Inc., 109 Md. App. 569, 580 (1996), in which
the court had stated that, in order to establish a lien under Section
9-102(a), a contractor must demonstrate 'that its repairs constituted
at least [fifteen percent] of the value of the building repaired.'
The Court of Special Appeals disagreed that Westpointe Plaza controlled
the outcome of the contractor's suit, stating that the general language
relied upon by the owner was not meant to decide the precise question
presently before the court. Then, tracing the legislative
history of Section 9-102(a) from its original
enactment in 1898, the court found that previous
versions of the statute had always clearly indicated that
the cost of all renovations to a property were to be considered
when determining whether the applicable percentage threshold had
been satisfied.
The holding in O-Porto Construction clarifies any confusion
which may exist over the proper application of Maryland's 15% rule.
As the court held, any contractor working on property that has been
repaired or improved to the extent of 15% of its value is entitled
to establish a lien under Maryland law, regardless of the value
of the individual contractor's work.
|
|
 |
 |
 |
|