Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     4        

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

WHEN LABOR IS NOT CONSIDERED LABOR FOR THE
PURPOSES OF THE VIRGINIA MECHANIC’S LIEN STATUTE

The Circuit Court for Hanover County, Virginia recently invalidated a mechanic’s lien filed by a contractor for costs incurred in preparing for the construction of a steel building where none of the contractor’s materials or labor actually reached the building site or were incorporated in the structure.

In Dallan Construction, Inc. v. Super Structures General Contractors, Inc., Hanover County Circuit Court, Case Number CL08000473-00 (January 30, 2009), Dallan Construction, Inc. (“Dallan”) filed a petition to invalidate the mechanic’s lien filed by Super Structures General Contractors, Inc. (“Super Structures”). Super Structures had entered into an agreement with Dallan for the construction of a steel building and, in accordance with the agreement, commenced preparatory work on the project. Before Super Structures began the actual construction of the project, Dallan cancelled its contract with Super Structures. While Super Structures had commenced the fabrication of steel components for use in the planned building project, none of its “means, methods, or products” had actually reached the building site at the time of termination. Thus, Dallan argued that Super Structures’ lien was invalid because it had not performed any labor or furnished materials to the property subject to the lien.

The court first observed that Virginia Code § 43-3 could be applied to the factual circumstances of this case because Super Structures performed labor or furnished materials for the construction of a building to be permanently annexed to the free-

hold, much like an architect or engineer’s efforts. Further, the labor and materials produced by Super Structures corresponded with Super Structures’ contractual obligations. The court noted, however, that the Supreme Court of Virginia has uniformly held against the imposition of a mechanic’s lien where the labor or materials claimed in a mechanic’s lien never actually reach the burdened property.

Super Structures claimed that it satisfied the “performing labor” requirement of Virginia Code § 43-3 through its preparation for fabrication of steel components to be used in the planned building project and was, therefore, entitled to lien the property. The Court rejected this argument, finding that, since Super Structures’ fabricated steel never reached the building site, it could not base its lien on such work.

Next, Super Structures asserted that it was entitled to a lien by virtue of the planning and design work it performed. Though the court acknowledged that the mechanic’s lien statute permits a claimant to lien for design work performed on a project, the court concluded that such lien rights must be conditioned upon the design efforts specifically enhancing the value of the burdened property. As Super Structures’ planning and design work was never incorporated or used in the building actually erected on the property, such design efforts could not be the foundation of a valid mechanic’s lien.

                         
continued on page 3

 

<< Prev     4