Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
March/April 2009 Volume XIV  Number 2

ACCORD AND SATISFACTION: BEWARE OF SUSPICIOUS
LANGUAGE ACCOMPANYING PARTIAL PAYMENTS

If an owner disputes a contractor’s final billing, the owner may attempt to resolve the payment dispute by tendering a check in an amount less than that claimed by the contractor, and indicating on the check itself that the account is being “paid in full.” But what effect, if any, would this language have on the contractor’s ability to collect the remainder of the amount due? In Helton v. Phillip A. Glick Plumbing, Inc., ___ Va. ___ (February 27, 2009), the Virginia Supreme Court addressed this issue, holding that such conspicuous language on the check amounts to an “accord and satisfaction” of the contractor’s claim and, therefore, by accepting the check, the contractor waives his right to collect the remainder of the amount invoiced.

In Helton, Phillip A. Glick Plumbing, Inc. (“contractor”) contracted with Michael Helton (“owner”) to perform certain plumbing services and to install a hot water heater in the owner’s home. Due to his observation that the contractor’s workers “were taking extended breaks and generally working slowly,” the owner kept close tabs on the time spent by the contractor installing the water heater. Upon receiving the contractor’s invoice, the owner objected to the amount billed, stating that the invoice was “considerably high based on the hours worked, multiplied by the rate per hour.” Accordingly, the owner “paid for the hot water heater installation but did not pay for all of the hours billed for the work.”

Subsequently, the owner sent two letters to the contractor regarding the owner’s complaints of overbilling and “allegations of ‘goofing off’ and wasted materials.” Finally, the owner mailed a cashier’s check to the contractor “in the amount of $1,300.00, which was $1,686.51 less than the amount billed” in the contractor’s final invoice with the words “Paid in Full” on the memo line of the check. Further, the owner transmitted the check with a letter stating that no more payments would be made due to concerns of overbilling and lack of efficiency in the installation of the hot water heater. Upon receipt of the check, the contractor crossed out the words “Paid in Full” and added “No” and “Balance Due $1,686.51” on the check before depositing it.

The contractor sued the owner for $1,686.51. The owner defended on the basis that the contractor’s acceptance of the owner’s check constituted an accord and satisfaction by use of an instrument. “In order to prove an accord and satisfaction by use of an instrument,” the

Virginia Supreme Court explained, “the person against whom the claim is asserted, the debtor, must prove that: (1) he in good faith tendered an instrument to the claimant as full satisfaction of the claim, (2) the amount of the claim was unliquidated or subject to a bona fide dispute and (3) the claimant obtained payment of the instrument.” Va. Code § 8.3A-311(a). The Circuit Court rejected this defense, finding that the owner had not acted “in good faith with an honest belief that a bona fide dispute existed.” The owner appealed to the Virginia Supreme Court.

The court overturned the circuit court’s decision, finding that, by virtue of the owner’s two letters concerning overbilling and goofing off, a bona fide dispute existed. Further, the court observed that, on the face of the check and in the letter transmitting the check, the owner conspicuously explained that the check was being tendered in full satisfaction of the claim. Accordingly, the court concluded that there had been an accord and satisfaction.

The only issue remaining, therefore, was whether the contractor’s alteration of the owner’s check justified the contractor’s argument that “acceptance of the check was for a partial

                         
continued on page 2

        1     Next >>