Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     4        

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

BOND CLAIM DENIED DUE TO UNTIMELY NOTICE

Owners and general contractors can protect themselves effectively against another party's default through the use of performance bonds, surety bonds, and supply bonds. However, if the beneficiary of the bond ignores notice requirements, or any other conditions precedent, the security afforded by the bond will be lost. New Viasys Holdings, LLC, v. The Hanover Insurance Co., 2007 U.S. Dist. LEXIS 17924, demonstrates that courts will not allow beneficiaries to recover against bonds when the beneficiary fails to adhere to the bond's conditions precedent.

In New Viasys Holdings, the Virginia Department of Transportation ("Owner") hired New Viasys Holdings, LLC ("Contractor") in April of 1999 to perform construction on various highways in the Hampton Roads area of Virginia. Contractor entered into a purchase order agreement (the "Purchase Order") with Supplier ("Supplier") in late March of 1999 for the supply of signs, equipment and support on the project. Supplier posted a supply bond (the "Bond") issued by The Hanover Insurance Co., ("Surety") naming Contractor as the beneficiary. The Bond allowed Contractor to seek damages against Surety in the event that Supplier defaulted under the Purchase Order. The Bond contained a number of conditions, including a requirement that Contractor could not claim against the Bond without providing immediate written notice of Supplier’s default to Surety.

In August of 2003, Supplier failed to provide materials in accordance with the Purchase Order; Contractor, however, provided Supplier an opportunity to remedy its breach. For thirteen (13) months, Supplier failed to remedy. On September 17, 2004, therefore, Contractor finally sent a letter to Surety, asserting a claim against the Bond, documenting Supplier’s breach.

After failed attempts between Contractor and Surety to resolve the matter, Contractor filed an action in federal court seeking payment under the Bond. Surety, in turn, filed a motion for summary judgment, arguing that Contractor failed to provide immediate written notice of Supplier's breach, as required by the Bond. Contractor responded by arguing that Supplier's defaults were continuing in nature and, additionally, that Contractor provided notice immediately upon Supplier's failure to cure its defaults.

The court granted Surety's motion, explaining that the Bond clearly used the term "immediate notice" as a condition precedent to a claim against the Bond. Though the court construed the term "immediate notice" as providing Contractor a reasonable time in which to provide notice of Supplier's breach, Contractor's failure to give notice of Supplier's first default within a reasonable time precluded Contractor's claim against the Bond. Therefore, the court held that Contractor's claim against the Bond was deficient.

This case serves as a reminder that bond provisions need to be reviewed and fully complied with or beneficiaries run the risk of having the bond's coverage denied by Courts.

<< Prev     4