Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
March/April 2008 Volume XVIII  Number 2

WHEN A CONTRACTUAL DESCRIPTION IS NOT ENOUGH:
QUALIFYING AS A SUBCONTRACTOR UNDER THE MILLER ACT

Suppliers of labor and materials for construction projects for the Federal Government do not enjoy the protection of mechanics' liens. A century ago, Congress responded to this problem by enacting the Miller Act, 40 U.S.C. 3131, et seq., which, in relevant part, requires contractors to furnish a payment bond to protect suppliers and subcontractors on Federal Government projects. Such a payment bond protects suppliers of labor and materials "having a direct contractual relationship with a subcontractor but no contractual relationship… with the contractor" against nonpayment. However, only if a subcontractor qualifies as a "subcontractor" under the Miller Act does the Miller Act bond protect the suppliers. Consequently, general contractors faced with a bond claim by a supplier may argue that the bond does not protect their suppliers and other subcontractors.

In a recent case decided by the Third Circuit Court of Appeals, United States ex rel. E & H Steel Corp. v. C. Pyramid Enterprises, Inc., 509 F.3d 184 (3rd Cir. 2007), the Army awarded the general contractor ("General Contractor") a contract to build a facility for aircraft maintenance at a base in New Jersey. General Contractor posted the requisite Miller Act bond and contracted with Havens Design-Build ("Havens") to provide custom-fabricated steel, prepare shop and erection drawings, design connectors for the steel, and perform design-assist engineering. Havens, in turn, contracted with E & H Steel Co. ("E&H") to fabricate and deliver the steel directly to the job site. Upon delivery, General Contractor erected the steel frame and self-performed most of the remaining construction work.

General Contractor paid Havens, but before Havens paid E&H, Havens filed for bankruptcy. E&H sued on the General Contractor's Miller Act bond. General Contractor defended on the grounds that Havens was not a "subcontractor" under the Miller Act, and thus E&H, Havens' steel fabricator, could not collect on the bond.

Although many owners and general contractors on a private construction job would consider Havens a subcontractor, the Miller Act provides a specific definition of "subcontractor." Under the Miller Act a "subcontractor" is "one who performs for and takes from the prime contractor a specific part of the labor or materials requirements for the original contract." The Third Circuit explained that "subcontractor" status applies to those (a) who perform specific parts of the original contract and (b) who have a substantial and important relationship with the contractor.

In E & H Steel, General Contractor argued that Havens did not qualify as a "subcontractor"

because its work was not "substantial" in relation to the rest of the project and because the general contractor, not Havens, performed most of the erection work. Therefore, General Contractor reasoned that Havens could not claim to have taken part of the labor or materials requirements from General Contractor, thereby precluding a claim by E&H, a mere supplier to Havens.

Nevertheless, the Third Circuit found that Havens was a "subcontractor" for Miller Act purposes. Although Havens did not construct the building or fabricate the steel, Havens did arrange for its design and delivery. Moreover, Havens prepared crucial shop and erection drawings, designed connectors, and performed design-assist engineering. Havens' timely completion of its work affected the project's completion time. The court found that, although Havens' work amounted to less than 8% of the contract price, "total project costs is not a weighty reason to deny recovery." Having found that Havens qualified as a subcontractor under the Miller Act, the Third Circuit concluded that E&H, as fabricator, could recover under the Miller Act bond.

Though not every subcontractor on a Federal Government project necessarily qualifies as a "subcontractor" under the Miller Act, the Third Circuit's recent decision indicates that the courts will extend the protection of the Act liberally to protect subcontractors who perform work on a project, even if little physical labor is involved. Thus, a subcontractor who performs a small amount of work will be considered a "subcontractor" if its work constitutes a "substantial" portion of the work that the general contractor does not perform itself. Consequently, contractors, subcontractors, and sureties should be on notice that courts may treat subcontractors performing comparatively minor work involving little or no actual physical construction as protected by the Miller Act.


        1     Next >>