Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     3    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

GENERAL CONTRACTOR CANNOT RECOVER
ADDITIONAL COSTS FROM OWNER FOR DEFECTS
IN DESIGN DOCUMENTS DUE TO UNTIMELY NOTICE

A general contractor may be foreclosed from recovering additional costs from an owner due to design defects if the general contractor fails to provide timely written notice of the claim as required by the contract. This point is illustrated in the case of Starks Mechanical, Inc. v. New Albany-Floyd County Consolidated School Corporation, 854 N.E.2d 936 (Ind. Ct. App. 2006).

In this case, a general contractor entered into a contract with an owner to provide mechanical and plumbing services in connection with the expansion and renovation of a middle school in Indiana. After the parties entered into the contract, the general contractor discovered numerous defects in the design documents provided by the owner.

Initially, the general contractor submitted a Request for Information (“RFI”) to the construction manager as notice of the design defects and the resulting delays on the project. As construction on the project progressed, the general contractor continued to submit RFIs to the construction manager which provided notice of further design defects and delays on the project. The owner instructed the general contractor to proceed with construction and to correct any design defects. The general contractor responded by hiring an engineer to review the design documents and recommend changes. The general contractor did not include the engineering and redesign costs in the numerous RFIs it submitted to the construction manager.

Almost two years later and as construction on the project neared completion, the general contractor submitted a change order request and payment application to the construction manager; the general contractor sought additional payment for the engineering and redesign costs for the first time. The owner denied the general contractor’s change order request. As a result, the owner filed a declaratory judgment action to determine whether or not the general contractor was entitled to an additional payment given the general contractor’s failure to provide timely notice of its claim as required by the contract.

The general contractor asserted that it was entitled to additional payment despite the contractual notice provisions because it was seeking delay damages rather than additional costs under the contract. Unlike claims for additional costs, delay damages were not subject to the notice requirements of the contract.

The court ruled in favor of the owner and found that the general contractor was foreclosed from recovering engineering and redesign costs because the general contractor failed to provide timely notice as required by the contract. The court observed that the contract contained express language equating the treatment of claims for delay damages to the treatment of all other claims. Further, the court noted that the contract expressly required that claims for delay damages be made in accordance with the notice provisions governing all other types of claims.

The court recognized that the general contractor incurred substantial costs because of the defects in the design documents and the owner’s insistence that the contractor resolve any problems and proceed with construction as scheduled. However, the court found that in order to preserve its right to seek additional compensation for these costs, the general contractor was required to submit a claim within fourteen days of discovery of the defects/delays and to submit weekly updates thereafter.

The court noted that the general contractor first became aware of the defects in the design documents less than one month after it entered into the contract with the owner. Although the general contractor submitted numerous RFIs, none of the RFIs provided the owner with notice of the general contractor’s intent to make a claim for additional compensation. Accordingly, the court ruled in favor of the owner; the court found that the general contractor’s claim was foreclosed as untimely because the general contractor waited nearly two years following the discovery of the defects in the design documents to submit a request for additional payment as required by the contract.

Starks Mechanical is yet another reminder that contractors should pay special attention to the notice provisions in their contracts when making claims for additional compensation. Such provisions should be followed to the letter.

<< Prev     3    Next >>