July/August 2004 Newsletters

 

Katz & Stone, L.L.P. Construction Newsletter
July/August 2004

 

NO DAMAGES FOR DELAY CLAUSE HELD UNENFORCEABLE
WHEN THE DELAY WAS NOT CONTEMPLATED BY THE PARTIES

In Atlantic Coast Mechanical v. R.W. Allen Beers Construction, 592 S.E.2d 115 (Ga. 2003), the Georgia Court of Appeals reversed a trial court that, relying in part on a no damages for delay clause, had thrown out a subcontractor’s suit which sought compensation for increased labor costs allegedly incurred due to the actions of the general contractor. In short, even though the parties’ subcontract barred delay claims, and even though the general contractor had the right to sequence the work and modify the schedule, the Court of Appeals construed the subcontract to only bar additional compensation for delays and hindrances the subcontractor could have foreseen.

In May 1996, Atlantic Coast Mechanical (“subcontractor”) was hired by Beers Construction (“general contractor”) to perform heating, ventilation, air conditioning, and plumbing work for a construction project called the ‘Children's Medical Center’ in Augusta, Georgia. In April 1998, the subcontractor submitted a request for an equitable adjustment (REA) for increased labor costs it claimed to have incurred because of the general contractor’s disruptions. The general contractor denied the claim and asked the subcontractor to withdraw its REA.

Instead, the subcontractor sued. In the suit, the subcontractor claimed that the general contractor had forced it to perform work in a “radically different manner, method, and sequence” than it had originally contemplated when bidding on the project. The subcontractor claimed that it was unable to rough-in overhead piping and equipment with rolling scaffolds and manlifts, as it originally planned, because the concrete work was late and out of sequence. Further, when the work areas finally became accessible, the subcontractor alleged that the general contractor required it to accelerate by demanding that it double the size of its crews and work those crews overtime. At the same time, the general contractor allegedly hampered the subcontractor’s progress by instructing other trades to stockpile drywall and other materials in the subcontractor’s work areas. The subcontractor claimed that the general contractor's actions resulted in a significant increase in labor costs, which it sought to recoup in its REA.

Notwithstanding clauses in the subcontract giving the general contractor the right to set the schedule for the work and barring the subcontractor from claiming delay damages, the Georgia Court of Appeals found that the subcontract did not bar the subcontractor’s claims. The court allowed the claim to proceed because it found that these clauses: (1) applied only to delays and hindrances the subcontractor could have foreseen when it entered into the subcontract and (2) were silent on the subcontractor's right to additional compensation for costs caused by the general contractor's actions.

Atlantic Coast Mechanical illustrates the tendency of courts to carve out exceptions to the enforceability of no damages for delay clauses. An exception many courts rely upon to permit delay claims, notwithstanding a no damages for delay clause, involves any claim arising out of delays or events not contemplated by the parties at the time of contract formation. Thus, even in the face of a contract provision that shifts the risk of certain delays onto the party who is delayed, that party may yet have the ability to prosecute and recover on claims arising out of unforeseen or uncontemplated delays.

FEDERAL COURT FINDS FAULT WITH A CLAIM FOR DELAY
DAMAGES BASED PURELY ON MATHEMATICAL FORMULA

A recent decision by the U.S. District Court for the Southern District of New York reminds contractors seeking to prove damages for extended overhead that courts disfavor damage calculations based purely on a formula, with no connection to the costs actually incurred during the delay period. In MacQuesten General Contracting, Inc. v. HCE, Inc., 296 F.Supp.2d 437 (S.D.N.Y. 2003), the court held that a jury award of $149,065.72 based on such a formula was not supported by sufficient evidence and vacated that portion of the jury verdict.

MacQuesten arose from a contract between a property owner and MacQuesten General Contracting, Inc. (“general contractor”) for the construction of affordable housing units. The general contractor executed two subcontracts with a foundation subcontractor totaling almost three million dollars for foundation work and plank installation.

The subcontractor encountered unanticipated rock and unsuitable soil as it began excavating for the foundation. Then, as the project continued, the gap between the amount invoiced by the subcontractor and the total payments it received grew to approximately $1.3 million. When the subcontractor sent a notice of intent to file a lien on the project, the general contractor refused to allow the subcontractor to return to work. The parties then sued each other.

At trial, the jury denied the general contractor’s claims and awarded the subcontractor over $1.7 million, which included $149,065.72 for extended overhead damages. The general contractor moved to set aside the jury’s award, arguing that the award for extended overhead was improper because the subcontractor had used an impermissible formula for calculating delay damages.

The District Court agreed with the general contractor, holding that the subcontractor’s proof of its overhead damages was legally insufficient. According to the court, even when the amount of damages is difficult to determine, there must be a definite and logical connection between what a party claims and what that party is able to prove. In MacQuesten, the subcontractor had simply taken the amount of overhead it had projected for the contract, changed that amount into a per diem figure based on the length of the contract, and multiplied that figure by the number of days the work was delayed. The calculation was based only on unreliable price elements of the subcontractor’s bid, and was not supported by evidence that the delays at issue actually caused any increase in overhead. Finally, the court noted that the subcontractor did not claim that reliable evidence of the subcontractor’s actual costs was unavailable. Accordingly, the court held that the general contractor was entitled to a new trial on this element of the subcontractor’s damages.

MacQuesten shows the importance of contractors adequately documenting and developing their claims for damages. As MacQuesten illustrates, attempts to short-cut a properly supported claim presentation are likely to turn potential victories into sure defeats.

SUBCONTRACTOR SUCCESSFULLY LIMITS LIABILITY UNDER INDEMNIFICATION CLAUSE

Construction contracts often contain an indemnity clause which obligates the contractor to indemnify any number of entities for losses arising from a variety of events. In drafting or reviewing such provisions, one of the most important questions to bear in mind is whether such a clause is drafted so as to require the contractor to indemnify other entities for damages arising out of their own negligence. Contractors seeking to limit their liability will agree to indemnify losses caused only by their own acts or omissions. The case of Nusbaum v. City of Kansas City,100 S.W.3d 101 (Mo. 2003), illustrates a successful attempt to limit indemnification liability to such an extent.

In Nusbaum, an individual fell and sustained injuries on a walkway owned by a theater, which was adjacent to a construction project. The individual brought suit against the theater and the construction project’s general contractor on the theory that a light pole knocked down during construction had caused damage to the walkway which, in turn, had caused the individual’s fall. The general contractor then sued one of his subcontractors, who had knocked down the light pole. After all parties had settled the claims of the injured individual, the theater sought indemnification from the general contractor, and the general contractor then sought indemnification from the subcontractor. The trial court ruled in favor of the theater and general contractor, ordering the general contractor to indemnify the theater for the amount of the theater’s settlement with the individual and a portion of the theater’s attorneys' fees and expenses, and ordering the subcontractor to indemnify the general contractor for the general contractor’s indemnity obligation to the theater, the general contractor’s settlement with the individual and a portion of the general contractor’s attorneys' fees and expenses. The subcontractor appealed.

On appeal, the subcontractor argued that its subcontract with the general contractor did not require it to indemnify the general contractor’s own negligence. The subcontract’s indemnity clause, similar to that found in AIA Document A401, provided that the subcontractor had to indemnify the general contractor “against claims, damages, losses and expenses... but only to the extent caused in whole or in part by negligent acts or omissions of the Subcontractor, the Subcontractor's Sub-subcontractors, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss, or expense is caused in part by a party indemnified hereunder.” (emphasis added). The subcontractor contended that its liability was limited to only those claims, damages, losses and expenses caused by the negligence of the subcontractor or those under its supervision. The general contractor countered that, because the indemnity provision applies regardless of whether or not damages are caused in part by an indemnified party, the subcontractor was also obligated to indemnify the general contractor for damages caused by the general contractor’s own negligence.

Finding in favor of the subcontractor, the appellate court held that the trial court had read the subcontractor’s obligations under the indemnity clause too broadly. Relying on decisions of courts from other jurisdictions interpreting virtually identical AIA indemnification provisions, the court concluded that the phrase “to the extent” limits an indemnitor’s liability for damages to the indemnitor’s percentage of fault for the injuries giving rise to the damages. The court thus concluded that the subcontractor was only required by the AIA indemnity clause to indemnify the general contractor for that portion of the general contractor’s losses arising from the subcontractor’s negligence, and to hold otherwise would make meaningless the subcontract’s express limits on the subcontractor’s duty to indemnify. Because the general contractor conceded that it was due no amounts for its settlement with the plaintiff if the indemnity provision did not require the subcontractor to indemnify the general contractor’s own negligence, the court held that the subcontractor did not have to pay for the general contractor’s settlement. The court then remanded the case for determination of whether the theater’s settlement with the plaintiff included any monies paid to settle negligence claims attributable to the subcontractor. If so, the subcontractor’s obligation to indemnify the general contractor for the theater’s settlement would only extend to those monies.

Contractors who cannot avoid indemnification obligations in their agreements are encouraged to expressly limit their obligation to only those losses arising from their own negligence. Caselaw such as Nusbaum gives contractors hope that, with such a provision in place, they will only be held liable to the extent of their comparative fault.

 

FEDERAL COURT FURTHER DEFINES WHEN CLAIMS FOR DESIGN DEFECTS MUST BE BROUGHT UNDER VIRGINIA LAW

Under Virginia law, a plaintiff is permitted five (5) years to enforce a design defect claim based upon a written contract, commencing at the time the defect or condition causing the breach occurs, as opposed to the time when it is discovered. Previous court decisions have established that a cause of action for defective design in Virginia occurs, or commences, when the allegedly defective plans were approved or accepted by the plaintiff. The recent decision of a federal court in Lone Mountain Processing, Inc. v. Bowser-Morner, Inc., 2004 U.S. App. Lexis 6806 (4th Cir. 2004), affirmed this principle.

In Lone Mountain, a coal operation plant entered into a contract on November 5, 1991 with a design firm for the design of a coal slurry impoundment structure. The main function of the plant was to clean coal in preparation for shipment. After a lengthy period of regulatory review during the permitting process, the design firm’s design of the structure was approved on March 20, 1995. Consequently, on March 24, 1995, the design firm issued a final payment order to the coal operation plant. Under the contract between the parties, “upon acceptance and approval of the work,” the plant was to retain (10%) and forward the remainder of payment within fifteen days of approval and acceptance. On April 25, 1995, the plant paid the final payment order without exercising any right of retainage.

On June 5, 1996, the plant filled the impoundment designed by the design firm with coal slurry. During this operation a pipe collapsed and contaminated water escaped. Two months later, contaminated water again escaped from the slurry impoundment into an abandoned coal mine. The plant was ordered to suspend operation until repairs were made. After repairs were performed, the coal operation plant restarted its operations. Later that year, however, a massive leak in the impoundment allowed 3,000 gallons of contaminated water per minute to flow into a creek that fed into the Powell River, killing an estimated 11,000 fish. As a result of the release of the contaminated water into the Powell River, which had been designated by the government as a critical habitat area, the plant was fined $85,000 and ordered to pay restitution in the amount of $1,510,000.

On May 26, 2000, the plant sued the design firm in federal district court for breach of contract, claiming that it breached obligations under the contract by providing defective design services. The firm asserted Virginia’s five-year statute of limitations on design defect claims as an affirmative defense and moved to dismiss the complaint. The district court agreed with the firm and dismissed the case, finding that the plant had missed the deadline to sue by a month.

On appeal, the Court of Appeals for the Fourth Circuit affirmed the district court’s ruling. The Court of Appeals held that the contractual design defect claim accrued upon payment for the design by the owner because such payment constituted “approval and acceptance” of the design. According to the firm’s contract with the plant, “upon approval and acceptance of the work, the [plant] shall retain ten percent (10%) and forward payment of the balance within fifteen (15) days thereof.” The design firm issued its final payment order on March 24, 1995. In reply, the plant tendered full payment on April 25, 1995, thereby indicating approval and acceptance of the work. Accordingly, under applicable Virginia law, the plant’s defective design claims arose on April 25, 1995 and the window to bring suit closed on April 25, 2000.

Construction professionals should be aware of the limitations on suits for design defects in Virginia. Because the time to sue commences upon acceptance of plans, rather than upon discovery of the defect, a potential plaintiff may have very little time to bring suit once a latent defect is realized