Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
July/August 2009 Volume XIV  Number 4

VIRGINIA SUPREME COURT STRICTLY CONSTRUES STATUTORY
PROCEDURAL REQUIREMENTS FOR PUBLIC CONTRACTS

In the administration of public contracts, there may be more than one relevant statutory section setting forth requirements for perfecting an appeal. In the case of Viking Enterprise, Inc. v. County of Chesterfield, 277 Va. 104 (2009), the Virginia Supreme Court addressed one such situation, affirming the dismissal of a contractor’s appeal of a county’s disallowance of a monetary claim for failure to adhere to all procedural requirements set forth in the Virginia Code.

In Viking Enterprise, Inc., Viking Enterprise, Inc. (“Viking”), the general contractor, entered into a contract with the County of Chesterfield (the “County”) for the construction of a fire station. The contract was governed by the Virginia Public Procurement Act, Va. Code §§ 2.2-4300 et seq. During the course of the project, the County directed Viking to remove and replace a portion of the concrete floor of the fire station. Viking disputed the necessity of this work, arguing that the issue with the floor could be repaired without re-pouring concrete. Accordingly, Viking submitted a claim to the County in the amount of $86,531.00 for the work performed in completing the work directed by the County. By letter dated August 2, 2005, the County denied Viking’s claim.

On January 27, 2006, Viking filed a complaint in the Circuit Court of Chesterfield County, seeking a judgment against the County for the additional concrete work performed by Viking. The County responded by filing a demurrer and motion to dismiss, arguing that Viking had failed to comply with Va. Code § 15.2-1246 requiring that a claimant seeking to appeal a decision of a county disallowing a claim must serve written notice on the clerk of the county within thirty (30) days of learning of the decision and must post a bond to the county. Viking did not dispute the County’s contentions; rather, Viking argued that, pursuant to the Virginia Public Procurement Act, the only requirement for instituting legal action on contracts governed by this statute was to file the complaint in an appropriate court within six (6) months of a decision from a public body, such as the County’s decision of August 2, 2005. Viking, thus, reasoned that a conflict existed between the two sections of the Virginia Code and that, by filing suit within six (6) months of the County’s decision and complying with the Virginia Public Procurement Act, its appeal should be heard.

The Circuit Court of Chesterfield County rejected Viking’s logic, concluding that a conflict did not exist between the two procedural requirements and that Viking should have complied with both sections of the statute. As Viking only complied with the requirements of the Virginia Public Procurement Act, and not § 15.2-1246, the circuit court determined that it lacked jurisdiction to hear Viking’s claims and, therefore, dismissed the case.

On appeal, the Virginia Supreme Court affirmed the circuit court’s decision, holding that “when appealing from a county’s disallowance of a claim arising out of a contract covered by the Procurement Act, the claimant must serve written notice…and execute a bond…in accordance with Code § 15.2-1246…[and] then institute legal action…in accordance with Code §§ 2.2-4363(E) and -4364(E).” In other words, each statutory section imposed filing requirements for perfecting the appeal and Viking’s failure precluded the pursuit of its claim. The lesson to be learned from Viking Enterprise, Inc. is that Virginia courts will strictly construe procedural provisions of the Virginia Code related to appealing a county’s decision to disallow a claim arising out of a contract covered by the Virginia Public Procurement Act and that failure to perfect one’s claim in accordance with all statutory requirements can result in the loss of the claim.

        1     Next >>