Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     4        

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

COLORADO COURT OF APPEALS ALLOWS SUBCONTRACTOR TO
RECOVER, DESPITE EXISTENCE OF “NO DAMAGES FOR DELAY” CLAUSE

Whether through a failure to obtain qualified professional advice or through misplaced trust in a contractor, subcontractors occasionally sign an agreement whereby they contractually forego certain legal rights. An example of such a waiver of right is when a subcontractor agrees to a broadly worded “no damages for delay” clause. When this happens, the court is frequently placed in the position of having to decide whether to place greater merit on the bargained-for contract or the implied principles of contract law.

In Tricon Kent Co. v. Lafarge North America, Inc., 2008 Colo. App. LEXIS 673 (Colo. Ct. App. May 1, 2008), Tricon (“Subcontractor”) entered into an agreement (the “Subcontract”) with Lafarge (“Contractor”) to perform earthwork on certain highways in Douglas County, Colorado. As a part of the Subcontract, Subcontractor agreed to a “no damages for delay” clause, under which — Contractor argued — Subcontractor waived its right to recover additional compensation as a result of delays or interference (to Subcontractor’s performance) caused by the Contractor. At the completion of Subcontractor’s work, a dispute arose as to the amount due Subcontractor, as Subcontractor had experienced significant setbacks during construction.

At trial, Subcontractor alleged that Contractor had breached its implied duty of good faith and fair dealing by significantly delaying Subcontractor’s ability to perform its scope of work under the Subcontract. Specifically, Subcontractor argued that the scope of its work had changed during the performance of the Subcontract as a result of Contractor’s failure to properly schedule the project and that Contractor interfered with its performance and caused it to encounter significant obstacles and costly delays. The jury returned a verdict in favor of Subcontractor, which Contractor appealed.

On appeal, Contractor contended the trial court erred in denying its motion for a directed verdict due to the incontrovertible existence of the “no damages for delay” clause. Subcontractor countered that the “no damages for delay” clause was inapplicable, and that

even if it did apply, there was evidence that Contractor’s actions constituted active interference with the Subcontract. Contractor, by contrast, argued that, in order to show active interference, Subcontractor had to show that Contractor committed some affirmative, willful act, in bad faith, to unreasonably interfere with Subcontractor’s compliance with the terms of the Subcontract, a burden which Subcontractor could not meet.

The issue of a “no damages for delay” clause was one of first impression in Colorado. As a result, the appellate court placed considerable reliance on the opinions of other jurisdictions, the majority of which had previously upheld the validity and enforceability of “no damages for delay” clauses. The court noted, however, that the “no damages for delay” clause was to be strictly construed against Contractor, as the drafter of the contract.

The appellate court ultimately adopted a modern interpretation of active interference as an exception to a “no damages for delay” clause, under which Subcontractor only needed to show that Contractor committed an affirmative, willful act that unreasonably interfered with Subcontractor’s performance of the Subcontract. As the appellate court rejected Contractor’s argument that Subcontractor had to prove Contractor’s bad faith, it affirmed the trial court’s decision in favor of Subcontractor.

The decision in Tricon Kent is worth noting, as the Colorado court showed an interest in moving beyond the practice of strictly interpreting contracts, towards allowing subcontractors to recover rights that had been contracted away in cases where a contractor abuses its bargained-for privileges. Although the courts are likely to abide by the stated clauses of the contract, this case shows that some courts will consider the issues beyond the four corners of the contract when ruling on a contractual issue. As a practical matter, before relying on a “no damages for delay” clause, a contractor should verify the enforceability of such clauses in the jurisdiction governing the contract.
<< Prev     4