Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     2    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

DELAWARE FEDERAL COURT REQUIRES OWNER’S BAD FAITH FOR
SURETY’S PERFORMANCE BOND DEFENSE; STRENGTHENS PROCUREMENT ACT

In the recent case of RLI Insurance Company v. Indian River School District, et al., 2008 U.S. Dist. LEXIS 43303, the U.S. District Court for the District of Delaware addressed the scope of coverage of a performance bond where an owner’s failure to properly supervise the work of the general contractor resulted in overpayment.

In August of 2002, the Indian River School District (“Owner”), hired McDaniel Plumbing and Heating, Inc. (“General Contractor”) to perform certain mechanical work for the New Sussex Central High School (the “Project”). General Contractor secured payment and performance bonds in favor of Owner from RLI Insurance Company (“Surety”), in accordance with the Delaware State Procurement Act (the “Procurement Act”). Owner also hired Becker Morgan Group, Inc. (“Architect”) and EDiS Company (“Construction Manager”) to work on the Project. Pursuant to the prime contract (the “Contract”), payments to General Contractor were contingent upon the review and approval of both Architect and Construction Manager.

Over the course of two years after commencement of the Project, General Contractor fell behind schedule. Architect and Construction Manager, however, continued to approve payment applications. Consequently, Owner continued to pay General Contractor all amounts requested. Eventually, Owner terminated the Contract and submitted a claim to Surety for completion of the Project under the performance bond. Surety denied the bond claim, asserting that Owner did not comply with its contractual obligations when it issued payments to General Contractor in excess of the work actually performed. Subsequently Surety filed a declaratory action alleging breach of fiduciary duty and negligent misrepresentation by Owner.

Surety raised two arguments for judgment in its favor. First, Surety argued that overpayment by Owner to General Contractor

discharged Surety from its obligations under the performance bond. The Court observed that older cases have held that “sureties should be granted a total discharge from their obligations in the event of overpayment” (citations omitted); however, the Court noted that the modern rule provided that “where there has been a material departure from contractual provisions relating to payments and the security of retained funds a compensated surety is discharged from its obligations on the performance bond to the extent that such unauthorized payments result in prejudice or injury.” (Emphasis added). Additionally, the court stated “the defense does not apply when the owner has in good faith relied upon the certifications of its architects or engineers” (citations omitted).

In order to prevail on its theory, therefore, Surety would need to prove (a) Owner’s bad faith in relying on the certifications from Architect and Construction Manager and (b) that Surety was injured by the overpayments. The Court rejected Surety’s argument, as it did not find any evidence of bad faith on the part of Owner. Moreover, the Court cited Surety’s actual knowledge of the overpayments and inaction at the time they occurred as evidence of no injury.

Surety’s second argument pertained to the terms and conditions of the bond, which provided, in relevant part, that Owner was required to arrange a pre-default conference with Surety and General Contractor prior to terminating General Contractor. Surety argued that, by failing to comply with the terms of the bond, Owner was precluded from asserting a claim thereunder. As the Procurement Act does not provide for a pre-default conference, however, the Court held that Surety’s defense to the bond claim based on Owner’s failure to schedule a predefault conference was invalid, and Owner’s Motion for Summary Judgment as to that point was granted.

As illustrated in RLI Insurance, Owners must be vigilant to act in good faith in the administration of construction contracts, avoiding overpayments that might limit their right to assert a claim under a performance bond. Although the Owner was absolutely absolved of its poor project management in RLI Insurance, a slightly different set of facts could have proved fatal to its bond claim.

<< Prev     2    Next >>