Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
July/August 2008 Volume XVIII  Number 4

UNTIMELY OR DEFICIENT NOTICE MAY EQUATE TO A WAIVER OF CLAIM

A construction contract usually sets out clear and definite notice provisions addressing the procedures for the making and documenting of a claim. While contractors may neglect to strictly adhere to these procedures, favoring an informal notice procedure to the comparatively antagonistic procedures set forth in the contract, such an informal approach to contract administration may result in substantial loss to a contractor. In Starks Mechanical, Inc. v. New Albany-Floyd County Consolidated School Corp., 854 N.E.2d 936 (Ct. App. Ind. 2006), the contractor’s failure to follow the notice provisions set forth in the contract made its claim to be reimbursed for engineering costs associated with deficient specifications untimely and, therefore, it was waived.

In Starks Mechanical, Starks Mechanical, Inc. (“Contractor”) entered into a contract (the “Contract”) with New Albany-Floyd County Consolidated School Corp. (“Owner”) for the expansion, renovation, and improvement of a middle school. After only one month on the project, Contractor discovered certain alleged deficiencies in the design specifications and submitted to Owner a Request for Information (“RFI”) to provide notice of the alleged design defects and to request a time extension. Owner responded to Contractor by directing Contractor to complete the project and to correct the alleged defects.

Contractor submitted RFIs throughout the course of the project, but many of the RFIs failed to assert a claim for the design costs it incurred. Nearly two years after signing the Contract, and with the project wrapping-up, Contractor included a line-item in a payment application for “Engineering Deficiencies” resulting from the Owner’s responses to the RFIs. This was the first formal notice provided to Owner of the actual costs incurred by Contractor associated with redesigning certain deficient specifications.

At trial, the court granted summary judgment in favor of Owner, finding that Contractor’s claim for additional payment had been waived due to its failure to provide timely written notice of its claim in accordance with the Contract. Contractor appealed the trial court’s decision to the Court of Appeals, arguing that the trial court misinterpreted the Contract and, that by submitting RFIs, the Contractor provided the requisite contractual notice.

The Court of Appeals held, first, that a request for information did not amount to notice of a claim. Specifically, the Contract provided that “Claims” must be made “within 14 days after occurrence of the event giving rise to such claim or within 14 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later.” Although the RFIs submitted by Contractor may have been timely, the RFIs did not claim additional engineering costs resulting from the design deficiencies. As such, the RFIs failed to provide Owner with notice of the claim for additional engineering costs within the fourteen days mandated by the Contract.

While the Owner may have known that correcting deficient specifications required Contractor to incur engineering fees, the purpose of such notice provisions is to alert an owner as to the cost of their decision so that the owner has an opportunity to make decisions with the bottom-line in mind. In failing to alert Owner as to the true financial impact of its decision, Contractor failed to provide Owner the information mandated by the Contract; therefore, the Court rejected its claim.

Moreover, the Court of Appeals found that Contractor failed to submit weekly updates of its claim, as required by the Contract. The Contract provided that “[i]n the case of continuing delay, the Claim along with estimated associated costs must be updated weekly and submitted to the Construction Manager for the duration.” Contractor admitted its failure to provide weekly updates as to the estimated costs associated with its ongoing claim for correcting deficient specifications. Coupled with the failure to request additional engineering costs resulting from the deficient specifications, the Court of Appeals determined that Contractor’s claim for additional compensation was untimely.

Having concluded that Contractor’s claims were untimely, the Court of Appeals affirmed the trial court by finding that Contractor’s failure to adhere strictly to the notice requirements of the Contract amounted to a waiver of those claims. Of note, the Contract did not include an express provision providing that failure to make a claim within the provided period equates to a waiver of claim. The Court of Appeals, therefore, did not rely on language expressly equating deficient notice with waiver of a claim as found in some construction contracts. Rather, the Court of Appeals construed the existence of a time period in which to make a claim as evidence that the parties intended to treat untimely claims as waived.

Starks Mechanical is instructive on many common contractual issues. First, although many contractors attempt to remove language from a contract equating deficient notice with waiver of a claim as a means of protecting their rights to make untimely claims, courts may elect to reject claims from contractors which fail to adhere strictly to the contractual notice requirements. Second, contractors should recognize that, although tedious and formal, failure to adhere to the notice provisions of a contract can have severe consequences. While this case was decided in Indiana, the logic behind the Court of Appeals’ decision could be applied by any court in this country. As such, contractors and owners alike should heed this ruling when negotiating and performing construction contracts.





        1     Next >>