Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     2    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

NOT ALL WORK TOLLS THE LIMITATIONS
PERIOD UNDER THE MILLER ACT

A contractor must file a payment bond claim under the Miller Act within one year of the last day that labor was performed or materials were supplied to the project. A recent decision by the United States District Court for the District of Columbia reveals just how strict the courts can be in applying the Miller Act’s statutory limitations period. In Highland Renovation Corp. v. Hanover Ins. Group, 620 F. Supp. 2d 79 (D.D.C. 2009), a contractor brought an action against the surety under the Miller Act on October 22, 2007 for money allegedly owed to the contractor for work performed in renovating the Old Post Office Pavilion in Washing ton, D.C. (the “Project”).

The surety immediately sought to dismiss the complaint on the grounds that the court lacked subject-matter jurisdiction over the contractor’s claim because the contractor had failed to timely file suit. Courts have routinely held that only work furnished as a part of the original contract tolls the one-year statute of limitations. Thus, the determinative question for a court in reviewing a Miller Act claim is whether the last date of work consisted of original contract work or was “remedial or corrective work or materials, or inspections of work already completed,” which most likely would not extend the Miller Act’s statute of limitations. As an additional element of consideration the court added that “the key is not whether the work was performed on the contract but whether the work that was performed was significant or crucial to the operation of the project.” Therefore, warranty work or punchlist work typically cannot be relied upon in es tablishing the last date of work for a Miller Act claim.

The surety submitted with its motion invoices reflecting that work was performed on the Project no later than July 2006, as well as a certified payroll record showing that the latest work on the Project occurred on July 28, 2006. In order to establish that the last date of work fell within the one-year period, the contractor submitted, in addition to other evidence, a series of its payroll sheets, which indicated that it had performed some work on the Project. The court, however, found that the payroll sheets bore no indicia of the nature of the work for which the wages were paid or when such work took place.

Specifically, the court addressed one payroll sheet that contained the statement “Millwork as of 10-23-06.” Although the date specified was within the one-year limitations period, the court determined that such evidence could only be relied upon for demonstrating that work was engaged in before October 23, 2006. Further, the contractor asserted that certain of its payroll sheets contained a certification by one of its subcontractors that work was

performed between October 2 through October 26; however, the court interpreted the representation to mean that the subcontractor merely certified that its payroll period was between October 2 and October 26, not that work was necessarily performed on such dates. Thus, the court found that the payroll records could not be relied upon as they failed to contain any evidence as to the nature of work performed and the dates upon which such work was furnished to the Project.

Additionally, the contractor asserted that the work performed was not exclusively punchlist work, but rather, included certain change order work. In support of this contention, the contractor submitted a memorandum of its project manager to the contract administrator for the Project stating that “there are a few items that have been put on the punchlist for phase 1 and phase 2 that are not punchlist items, they are change orders.” Although the alleged change order work may have stayed the tolling of the Miller Act statutory limitations period, the court found that the memorandum could not be relied upon as it failed to distinguish between the work that was corrective or remedial punchlist work, and that which was change order work.

Thus, the court ruled that the contractor’s claim must be dismissed as no sufficient evidence was submitted by the contractor to contradict the surety’s assertion that work on the Project was completed in July, 2006. This ruling makes clear the necessity to maintain detailed project records as such documents can later be used to establish the last date of work for a Miller Act claim.

                         
continued from page 1

the date of final payment to F&M. According to the evidence, final payment did not occur until November 14, 1997. Again, the court rejected Roy Farms’ argument. The court reasoned that the date of final payment was irrelevant when specific evidence of not only substantial completion, but total completion of the project was presented. In the end, the court affirmed the trial court’s finding that the claims were barred by the statue of repose. Since the windstorm that damaged Roy Farms’ warehouse occurred on October 29, 2003, its claims against both defendants were beyond the six-year limit set forth in the statute of repose.

It is important to reiterate the difference between a statute of limitations and a statute of repose. Although the statutes vary from state to state, the time period contained within a typical statute of limitations begins to run when the injury to the aggrieved party occurs. On the other hand, under a typical statute of repose, the applicable time period commences upon the completion of an act. As shown above, the “act” contemplated under Washington law was the later of substantial completion or termination of services. This distinction is important to remember, particularly in construction-related litigation, where a claim could end up being barred by the statute of repose even before the injury occurs.

<< Prev     2    Next >>