Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
K A T Z   &   S T O N E ,  L . L . P .
8 2 3 0  L e e s b u r g  P i k e ,  S u i t e  6 0 0 ,  V i e n n a ,  V i r g i n i a  2 2 1 8 2
7 0 3 . 7 6 1 . 3 0 0 0  F a x  7 0 3 . 7 6 1 . 6 1 7 9  w w w . k a t z a n d s t o n e . c o m
Construction Newsletter
January/February 2010 Volume XV  Number 1

STATUTE OF REPOSE BARS CONSTRUCTION
CLAIMS IF NOT TIMELY ASSERTED

In civil litigation, an injured party must pursue its rights within the timeframe established by the applicable statute of limitations, which sets forth the period within which a plaintiff must file suit or have its claim forever barred. The exact period of time varies from jurisdiction to jurisdiction and may depend on, among other things, the nature of the claim (e.g., breach of contract or personal injury), the place where the harm occurred, and when the injury was discovered. Additionally, many jurisdictions have similar laws known as “statutes of repose.” A statute of repose, by contrast to a statute of limitations, terminates a right of action after a specific time, even if no injury has yet befallen the plaintiff. In the case of Roy Farms, Inc. v. F&M Construction Co., 2010 Wash. App. LEXIS 49 (2010), the State of Washington’s statute of repose highlights the need to timely pursue one’s legal remedies, particularly in the context of construction litigation.

In Roy Farms, Roy Farms, Inc. (“Roy Farms”), as owner, contracted with F&M Construction Co. (“F&M”), as general contractor, to rebuild two cold storage warehouses in 1997. F&M self-performed certain elements of the work and subcontracted with two subcontractors to perform certain metal roofing and refrigeration equipment installation. F&M completed the project on or about October 24, 1997. On October 29, 2003, just over six (6) years later, a windstorm damaged the warehouses’ roofs, which had been installed by Continuous Gutter (“CG”), a subcontractor to F&M. In January of 2005, Roy Farms sued F&M and CG for damages, alleging that F&M breached the construction contract and that CG was negligent in the installation of the metal roofs.

In response to the complaint, F&M and CG filed motions for summary judgment seeking to dismiss the complaint on the grounds that the Roy Farms’ claims were time barred by Washington’s statute of repose because they occurred more than six (6) years after the project achieved substantial completion. The trial court agreed with the defendants and granted their motions for summary judgment, dismissing Roy Farms’ case. Roy Farms then appealed the trial court’s deci sion. On appeal, the Court of Appeals of Washington addressed whether the trial court erred in finding Roy Farms’ claims barred by the six-year statute of repose. In addressing the

issue, the court first considered the applicable statute of repose. Specifically, under Washington law, any claim or cause of action arising from the construction or improvement upon real property must be brought within six (6) years of the later of either substantial completion or termination of services. Under Washington law, substantial completion is achieved when the property “may be used or occupied for its intended use.” The court noted that substantial completion must apply to the entire improvement, and not just a discrete component. Additionally, occupancy is not required for substantial completion to have been reached.

The evidence taken by the trial court indicated that work on the project was completed no later than October 24, 1997. Under the court’s interpretation of the statute of repose, whether or not Roy Farms actually used the buildings was irrelevant, as upon achievement of substantial completion, the buildings “may have been used” for their intended purpose. Roy Farms’ principal argument against application of the statute of repose was that it had not made use of the warehouses until well-after October 24, 1997. The court disagreed with Roy Farms.

Roy Farms also argued that “termination of services,” as contemplated under the statute of repose, had not occurred until

                         
continued on page 2


NOT ALL WORK TOLLS THE LIMITATIONS PERIOD
UNDER THE MILLER ACT


♦♦

INCORPORATED DOCUMENTS:
UNREAD CONTRACT DOCUMENTS
CAN CAUSE HEADACHES

♦♦

THE UNINTENDED FORMATION OF A PARTNERSHIP
OR JOINT VENTURE

 

        1     Next >>