Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     4        

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

Claims Vs. Changes: Understanding the Rules of the Game

In the recent case of Steel Service Corporation v. Board of County Commissioners of Hamilton County, 2007 U.S. App. LEXIS 30052 (6th Cir., December 27, 2007), the Sixth Circuit considered the distinction between claim provisions and change order provisions under a construction contract. Ultimately, the Court distinguished between claims and change orders, holding that signing a change order does not preclude a party from making a claim on that subject.

Steel Service Corporation ("Contractor") entered into a contract (the "Contract") with the Board of County Commissioners of Hamilton County, Ohio (the "Owner") to construct the steel superstructure for the Cincinnati Reds new baseball stadium, the Great American Ball Park (the "Project"). The Contract initially called for payments to Contractor of approximately $33 million. During the course of construction, Owner directed Contractor to take "extraordinary measures, including the provision of additional manpower, shifts, overtime and equipment" in order to expedite construction. Contractor subsequently informed Owner that it would be submitting a claim for the resulting costs and, in accordance with the relevant provisions of the Contract, submitted the claim to Owner (the "Claim").

The Claim requested an additional $5 million as compensation for the extraordinary measures taken by Contractor beyond the scope of the Contract. Owner, disagreeing with this assessment, delayed making a decision on the Claim. Prior to resolving the Claim, the parties executed a valid change order, which, by its terms, constituted a "full, final and complete waiver and settlement with respect to any and all claims, demands and causes of action of [Contractor] arising out of the Changes." Owner asserted that the change order settled all construction change proposals submitted by Contractor, including the Claim.

Upon substantial completion, Contractor filed suit against Owner to recover its $5 million Claim. Owner responded, arguing that the change order precluded any recovery on the Claim because the Claim amounted to a construction change proposal addressed by the express terms of the change order. Owner also argued that Contractor's Claim included the "pass-through" claims of Contractor's subcontractors, which should be precluded given the lack of privity of contract between the subcontractors and Owner. The trial court granted summary judgment in favor of Owner, persuaded that the change order precluded Contractor's recovery of its Claim.

On Appeal, the United States Court of Appeals for the Sixth Circuit conducted a detailed review of the contractual provisions regarding making claims and executing change orders. In doing so, the Sixth Circuit highlighted the inherent differences between the construction change proposal/change order process and the process for making a "claim" under the contract. The Sixth Circuit stressed that a claim in most circumstances, including the instant case, is defined in the contract as a demand for compensation that a party believes it is entitled to under the contract. As such, a claim is broader than a right to adjustment under a particular change order. The Sixth Circuit found, therefore, that signing off on the change order did not preclude Contractor from making its Claim. Contractor properly brought the adjustment for the extraordinary measures required by Owner in its Claim, despite the existence and validity of the change order.

General contractors and owners of projects alike should take note of the Sixth Circuit's holding in Steel Service Corporation and recognize that courts may treat the change order process and claims process as separate forms of demand for payment.

<< Prev     4