Download a PDF
To obtain a printable copy of this newsletter, please click on the "Download a PDF" button above.
<< Prev     2    Next >>

A  P u b l i c a t i o n  b y  K A T Z   &   S T O N E ,  L . L . P .
Construction Newsletter

Subcontractor or Supplier, an Important Distinction

The distinction between a subcontractor and supplier is not always clear, though the distinction can be important in determining parties' rights. This is especially true with regard to asserting a claim under a payment bond. In U.S. ex rel. Md. Minerals & Cranseville Stone Co. v. U.S. Fid. Guar. Co., 2007 U.S. Dist. LEXIS 41893 (N.D. W. Va. June 8, 2007), the court looked beyond the contracts and applied a balancing test to determine whether a concrete company was a subcontractor or a supplier for the purpose of determining whether it could make a claim on a payment bond.

The Federal Government contracted with P.J. Dick ("Contractor") to build a Federal penitentiary in West Virginia (the "Project"). The Contractor obtained a bond ("Bond") issued by USF&G ("Surety") for the project as required by the Miller Act. The Contractor selected Kimberly Concrete ("Kimberly") to supply concrete for the penitentiary's construction and the two entered into a purchase order agreement on February 7, 2001. Kimberly entered into a series of contracts with Maryland Minerals, Cranseville Stone Co., and Essroc, Inc. ("Plaintiffs") to obtain the necessary materials to produce concrete for the project. In late November of 2002, before the project was completed, Kimberly began having financial difficulties and ceased its business operations, leaving unpaid balances for materials delivered by the Plaintiffs.

Plaintiffs filed actions against Surety to collect on the Bond. Under the Miller Act, only suppliers of a subcontractor are able to recover under such a bond. As such, the issue before the court was whether Kimberly, the party with which Plaintiffs contracted, was a subcontractor or a supplier to Contractor. Surety argued that Kimberly was a supplier, not a subcontractor, and that Plaintiffs, as second-tier suppliers, were not entitled to recover under the Bond.

Plaintiffs relied on the language used in the contract between Contractor and Kimberly and in the contracts between Kimberly and Plaintiffs. Specifically, the contract between Contractor and Kimberly described Kimberly as

a "subcontractor". Moreover, Plaintiffs' contracts with Kimberly referred to Kimberly as "contractor". The court looked past the contractual language, and, instead, applied a balancing test to determine whether Kimberly was a subcontractor or supplier.

The court found persuasive the balancing test applied in U.S. for the Use and Benefit of Conveyor Rental & Sales Co. v. Aetna Cas. & Sur. Co., 981 F.2d 448 (9th Cir. 1992). This balancing test considers certain factors as indicative of a subcontract and certain factors as indicative of a supply contract.

The factors suggesting a subcontractor relationship include whether the product suplied is custom-fabricated; whether the product supplied is a complex integrated system; whether a close financial interrelationship exists with the prime contractor as evidenced by the requirement of shop drawing approval by the prime contrator; whether the supplier is required to perform on-site; whether there is a contract for labor in addition to materials; whether the term subcontract is used in the agreement; whether the materials supplied do not come from existing inventory; whether the supplier's contract constitutes a substantial portion of the prime contract; whether the supplier is required to furnish all the material of a particular type; whether the supplier is required to post a perofrmance bond; whether there is a backcharge for cost of correcting supplier's mistakes; and whether there is a system of progressive or proportionate fee payment.

The factors suggesting a supplier relationship include whether a purchase order form is used by the parties; whether the materials come from pre-existing inventory; whether the item supplied is relatively simple in nature; whether the contract is a small percentage of the total construction costs; and whether sales tax is included in the contract price.

The court, after applying the factors of the balancing test, found that Kimberly was a supplier. The court relied on the facts that Kimberly issued purchase orders, Kimberly included the sales tax in the contract price, Kimberly was not the sole provider of concrete for the Project, the concrete came from a pre-existing inventory, and Kimberly did not have to provide labor for the Project. Therefore, pursuant to the Miller Act, Plaintiffs, who were second-tier suppliers, were denied recovery from USF&G's surety bond because Kimberly was a supplier, not a subcontractor.

This case demonstrates that courts will not be bound strictly by the language of contracts in their determination of subcontractor or supplier status, but will closely examine the relationship of the parties considering a variety of factors.

<< Prev     2    Next >>