January 2001 Newsletter

 

Katz & Stone, L.L.P. Construction Newsletter
January/February 2001
Volume XI, Number I

 

REMEDIAL WORK AND CORRECTIVE TESTS ARE NOT "LABOR" FOR PURPOSES OF THE MILLER ACT STATUTE OF LIMITATIONS

Under the federal Miller Act, a claimant must file suit against the payment bond surety no later than "one year after the day on which the last of the labor was performed."  An issue often arises whether corrective work constitutes labor for purposes of this one-year statute of limitations.  In Interstate Mechanical Contractors, Inc. v. International Fidelity Co., 200 F.3d 456 (6th Cir. 2000), the U.S. Circuit Court of Appeals for the Sixth Circuit officially adopted the "correction-or-repair versus original contract" test as a framework for determining when the one-year statute of limitations begins to run.

The key facts are as follows.  In November 1993, the subcontractor entered into a contract to provide and install heating, ventilating, and air-conditioning systems at a U.S. Department of Commerce facility in Morristown, Tennessee (the "facility").  The prime contractor posted a Miller Act payment bond to guarantee payment under the contract.  In June 1994, the subcontractor completed its construction, including installation of two electric duct heaters.  In late September or early October 1994, while preparing final reports for the project, it was discovered that the ducts heaters were not performing to specification.  The subcontractor ultimately replaced the heaters in early October, which necessitated a third round of testing.  On October 18, 1994, the subcontractor's tester returned to the facility to confirm that the new heaters were functioning as specified.  Exactly one year later, on October 18, 1995, the subcontractor filed suit against the payment bond surety in federal district court in Tennessee to recover  the unpaid contract balance of $30,967.00. Under the Miller Act, suits to recover against a payment bond must be filed no more than "one year after the day on which the last of the labor was performed."  The issue before the court was whether the test of replacement components (the inspection and testing of the second set of heaters on October 18, 1994) qualified as "labor."  On cross-motions for summary judgment, the magistrate judge held that the subcontractor's complaint had not been filed within the Miller Act's one-year statute of limitations and dismissed the subcontractor's bond claim as untimely. 

On appeal, the 6th Circuit affirmed the magistrate's decision and officially adopted the "correction-or-repair versus original contract" test.  Pursuant to this test, remedial or corrective work or materials (or inspection of work already completed) does not toll the Miller Act's statute of limitations while work performed as "part of the original contract" will toll the statute.  Since the October 18, 1994 tests were of corrective work performed by the subcontractor, and thus not performed as part of the original contract, the court held that such tests were not "labor" for purposes of the Miller Act.

The test followed by the 6th Circuit court is utilized by a growing number of federal courts to determine statute of limitations questions under the Miller Act.  As such, prudent subcontractors should always take a conservative approach in deciding when to file suit on a bond claim.  As this case illustrates, subcontractors should endeavor to determine their last day of labor performed (not counting remedial or corrective work) as early in the process as possible and should strive to file suit sooner rather than later to avoid the harsh consequences of the Miller Act's statute of limitations.

 

NEW YORK APPELLATE COURT APPLIES AIA INSURANCE PROVISIONS

Construction contracts often assign responsibility to obtain the various types of insurance coverage needed on a project between the contractor and owner.  While the insurance provisions are not typically the subject of substantial negotiation, the operation of these clauses can have  significant financial consequences to the parties.  In the recent case, Mu Chapter of the Sigma Pi Fraternity v. North East Construction Services, et al., 709 N.Y.S.2d 677 (2000), a New York State appellate court applied the insurance provisions of the AIA general conditions in the aftermath of a jobsite fire. 

In Mu Chapter, a fraternity contracted with a general contractor to renovate the existing fraternity house and construct a four-story addition.  The very day the general contractor commenced work on the addition, a fire broke out which resulted in a total loss of the existing structure.  The fraternity received a payment of $670,000.00 from its property insurance carrier to cover the damages resulting from destruction of the existing fraternity house. The fraternity filed suit against the contractor alleging negligent use of acetylene torches and sought recovery of uninsured losses and consequential damages sustained as a result of the fire.  Additionally, the insurance carrier, as the subrogee of the fraternity, filed a separate suit against the contractor to recover the $670,000.00 paid to the fraternity covering the destroyed structure.  Following the joinder of the two cases, the contractor moved for summary judgment against both plaintiffs.  The trial court granted both motions and dismissed each claim in its entirety.  The plaintiffs appealed.

At issue in both cases were the terms of the insurance requirements contained in the AIA General Conditions (1987 version).  In defense of the fraternity's suit for uninsured losses, the contractor argued that Article 11 of the General Conditions required that the fraternity purchase property insurance in the amount of the contract sum, or notify the contractor of its decision not to purchase the insurance.  In the event of the fraternity's failure to do either, by virtue of Article 11.3.1.2, the fraternity was to "bear all reasonable costs attributable to such failure."  Thus, the contractor argued that the fraternity's failure to obtain the required property insurance barred its claim for uninsured losses.  The appellate court disagreed.

The Appellate Division of the Supreme Court of New York held that the purpose of the insurance required by Article 11 was to insure the value of the work performed at the time of loss, as well as any equipment and materials on site belonging to the contractor and any of the subcontractors.  Accordingly, the court held that the fraternity's breach of Article 11 did not preclude its claim for uninsured damages to the existing structure resulting from the contractor's negligence.  Instead, the fraternity's breach merely subjected it to liability to the contractor for the value of the contractor's destroyed work, materials and equipment.

The contractor further argued that pursuant to Article 11.3.7 of the General Conditions, the fraternity and contractor waived all rights against each other for damages caused by fire "to the extent covered by property insurance".  Although the court recognized that the Article 11.3.7 waiver applied to the money paid to the fraternity by its property insurance carrier, the fraternity's claim against the contractor was for uninsured losses, which had not been waived by Article 11.3.7.

With respect to the fraternity's claim for consequential damages, the contractor argued those claims had been waived by Article 11.3.3 which provides that the "owner waives all rights of action against contractor for loss of use of the owner's property, including consequential losses due to fire however caused."  As a result, the appellate court upheld the trial court's ruling that the fraternity was barred from pursuing any claim of consequential damages resulting from the fire.

Lastly, and with respect to the insurance carrier's subrogation claim, the appellate court held that the insurance carrier was precluded from seeking damages as a subrogee under the insurance policy.  The court cited Article 11.3.5 of the General Conditions which provides that if the owner insures property adjacent to the contract work under a policy separate and apart from the builder's risk policy required by the General Conditions, the owner waives all rights to damages caused by fire that were covered by the insurance policy insuring the adjacent property.  In this case, the court determined that the property insurance which covered the fraternity's existing structure was  insurance that was separate and apart from the insurance required by the contract.  Accordingly, the court held that the fraternity had waived any claims against the contractor for damages caused by the fire to the extent covered by insurance and that, as a result, the insurance carrier was barred from recovering against the contractor as a subrogee. 

The Mu Chapter case illustrates the important division of rights and responsibilities pertaining to insurance coverage found in the AIA General Conditions.  Contractors and owners need to be familiar with these provisions to ensure they have obtained proper insurance coverage for their projects and further that any losses which may be sustained are borne by the appropriate carrier.

 

VIRGINIA'S WORKERS' COMPENSATION STATUTE DOES NOT PRECLUDE AN OWNER'S EMPLOYEE FROM BRINGING A PERSONAL INJURY ACTION AGAINST THE ARCHITECT OR CONTRACTORS

Every state has laws that protect employees in the event they are injured on the job.  These  workers' compensation statutes give an injured employee the right to receive certain benefits for an injury directly from his or her employer regardless of fault.  Typically, the injured worker's remedy against its employer is limited to the relief authorized by the workers' compensation statute.  In many states, workers on a construction project are deemed to be statutory "fellow employees" of all contractors and subcontractors working on the project and an injured worker's recovery is thereby limited to workers' compensation benefits.  In Virginia, this exclusive remedy protection is limited only to those employers who are engaged in the same trade, business or occupation.

In the case of Stone v. Door-Man Manufacturing Company, 2000 Va. LEXIS 134 (2000), the Virginia Supreme Court addressed whether an injured employee of a project owner could bring a personal injury action against the project architect and various project contractors.  Given the particular facts found in Stone, the Court ruled that the statute did not preclude such a suit.

In Stone, an employee of Ford Motor Company was injured when an overhead door unexpectedly closed and struck him as he drove a tow-motor vehicle beneath it.  The employee was paralyzed from the mid-chest down. The door was located in a body shop that had been renovated several years earlier.  After recovering from his employer Ford under the workers' compensation statute, the employee then brought a personal injury action against the architect who had designed the door and various contractors who had either installed or manufactured the door during the renovation.  The suit alleged that the "inductive loops" which opened and closed the door automatically had been negligently designed and/or installed and sought compensatory and punitive damages in excess of $30 million.

In proceedings before the trial court, the various construction defendants moved to dismiss the suit.  The construction defendants argued that the plaintiff's employer, Ford, was engaged in the same trade business or occupation as them, that the plaintiff was a statutory fellow employee of  the defendants and therefore could not sue the defendants for his injuries.  Based on the fact that Ford did much of the initial design for the body shop, does some of its own design work on small construction projects and employs a sizeable number of skilled tradesmen that install doors similar to the one that caused the plaintiff's injury, the trial court held that the construction defendants were in the same trade or business as Ford and thereby could not be sued by the plaintiff.

On appeal, the Supreme Court reversed the trial court, finding that the defendants and Ford were not engaged in the same trade, business or occupation.  First, the court found that Ford was engaged in the business of manufacturing and selling motor vehicles and that the construction defendants were not engaged in that business.  Second, although recognizing that Ford had performed design and construction work similar to that of the defendants in the past, the court found that this limited construction activity was not part of Ford's "normal work."  The court found it significant that Ford historically contracted for design and construction services on larger projects, such as the renovation project that lead to the installation of the door at issue, and that none of Ford's own forces performed any construction services on the renovation at issue.  Thus, the court concluded that the plaintiff and the defendants were not in the same trade or business as Ford and that Virginia's statute did not bar the plaintiff's personal injury claims against the construction defendants.

The Virginia Supreme Court's holding in Stone illustrates the general rule that an injured employee may maintain a tort action against third-parties even though it has recovered workers' compensation benefits from its employer. The Stone decision further evidences the court's unwillingness to broaden the exclusive remedy protection of Virginia workers' compensation statute to owners, architects and contractors working on the same project.

 

WISCONSIN APPEALS COURT APPORTIONS "PREVAILING PARTY" ATTORNEYS' FEES RECOVERY

Construction contracts often contain a provision that should the parties to the contract institute litigation, the "prevailing party" is entitled to recover its attorneys' fees and litigation costs.  But, as a Wisconsin appeals court held in Sanfelippo Environmental Construction LLC v. Mews Companies, Inc., 616 N.W.2d 922 (Wisc. 2000), recovering only a nominal amount on a claim is not sufficient to be considered a "prevailing party."

In Sanfelippo, the general contractor for a highway project near Milwaukee, Wisconsin subcontracted with a landscape subcontractor to perform landscaping work.  When the general contractor refused to pay the subcontractor's claim for topsoil work performed, the subcontractor sued.  At trial, the prime contractor claimed that it had performed 95% of the topsoil work itself and the court ultimately accepted the testimony of the project owner's engineer that the prime contractor had performed 80% of the topsoil work.   Accordingly, the court awarded the subcontractor only 20% of its claim for topsoil work in the amount of $1,162.00.

Pursuant to the "prevailing party" clause of the subcontract, the trial court also awarded the subcontractor all of its attorneys' fees and costs in the amount of $23,261.20.  The general contractor appealed this award, claiming that the term "prevailing party" as utilized in the subcontract was ambiguous and that the court's "80/20" ruling on the topsoil work meant that neither party ' or both parties ' had actually prevailed.  In opposition to the general contractor's appeal, the subcontractor cited Wisconsin case law that defined a prevailing party as one who receives at least some of the relief it requests.  However, the appeals court relied on other case law for its finding that a "prevailing party" as to some, but not all, litigated issues can recover attorneys' fees and costs only as to the issues on which it was successful.  To hold otherwise, the court stated, would encourage contractors to bring large, mostly frivolous claims, and would produce unfair or unreasonable results.  On this basis, the appellate court concluded that the general contractor and subcontractor were both prevailing parties, and remanded the case to the trial court to award the general contractor 80% of its attorneys' fees and costs and the subcontractor 20% of its fees and expenses.

Successful litigants often view the losing side as responsible for their incurring the costs of litigation, and just as often hope, or even expect, to be reimbursed by the other party for those costs.  However, litigants are often disillusioned by the "American Rule," the nationwide standard that parties to litigation generally must pay their own costs and fees, except when a statute or contract provides otherwise.  In an effort to discourage frivolous claims, many contractors have incorporated "prevailing party" clauses into their contracts.  Although limited to Wisconsin, the Sanfelippo case illustrates the proposition that a nominal positive recovery does not necessarily make one a "prevailing party" for recovery of attorneys' fees.  Indeed, although the subcontractor ultimately recovered 20% of its claim and 20% of its attorneys' fees and costs, the subcontractor could very well end up reimbursing its opponent in an amount far greater than its recovery.