November/December 2003

Katz & Stone, L.L.P. Construction Newsletter
November/December 2003

MARYLAND COURT DISMISSES MECHANIC’S LIEN CLAIM
FOR FAILURE TO INCLUDE TIME OF PERFORMANCE OF WORK IN NOTICE OF INTENTION TO CLAIM LIEN

Generally speaking, statutory requirements governing the establishment of a mechanic’s lien are strictly interpreted and enforced by state courts. The case of Gravett v. Covenant Life Church, No. 01430 (Md. Ct. Spec. App. filed September 10, 2003), demonstrates that Maryland courts observe this general rule of strict application.

In
Gravett, a structural steel erection sub-subcontractor brought suit to establish a mechanic’s lien against a project owner’s property. Six months into its contract, the sub-subcontractor had sent a statutorily-required notice of intention to claim a lien to the owner, alleging that it had not been paid by the subcontractor for whom it had performed work on the project. Two months later, the sub-subcontractor sent a second notice of intention to claim a lien to the owner, identical to the first except that the outstanding balance claimed by the sub-subcontractor was reduced.

After the sub-subcontractor brought suit, the owner moved to dismiss the lien action on the grounds that the sub-subcontractor’s notices were defective for failing to state the time period during which the sub-subcontractor performed the work on which its claim was based, as required by Maryland’s mechanic’s lien statute. The trial court granted the owner’s motion and dismissed the sub-subcontractor’s lien claim, and the sub-subcontractor appealed.

On appeal, the sub-subcontractor argued that its omission from the notices of the time period worked was harmless and that the notices substantially complied with the law. The appellate court, however, held that under Maryland law, the failure of a lien notice to specify when the work was done is a fatal defect because such notices are designed to allow the owner to determine whether the claimant has a timely, and therefore a meritorious, lien claim. While recognizing that the Maryland Code endorses a form of lien notice which need only be substantially followed, the appellate court held that a notice omitting the time of the work’s performance is not in substantial compliance with the Code’s form.

The sub-subcontractor also argued that the omission from its notices of the time during which it performed the work at issue was unimportant because the owner had actual knowledge that the sub-subcontractor had performed its work within the statutorily-mandated period of time prior to issuance of the notices. The appellate court, however, concluded that the mere timing of the notices, neither of which stated the time the sub-subcontractor’s work was performed, did not ensure the owner’s actual knowledge of the time of performance of the work. Accordingly, the appellate court affirmed the trial court’s dismissal of the sub-subcontractor’s lien claim.

Most mechanic’s lien laws require precise detail in the notices and other documents that must be filed to establish and enforce a mechanic’s lien. Contractors need to ensure that all necessary information is included in their documents or, like the sub-subcontractor in
Gravett, they may find their otherwise compelling lien claim ruled invalid.

VERBAL NOTICE SATISFIES CONCEALED CONDITIONS NOTICE REQUIREMENT

Construction professionals familiar with the American Institute of Architects’ (“AIA”) form agreements know that the AIA’s General Conditions (A201) require contractors who discover concealed or subsurface conditions necessitating an adjustment to the contract price or time to provide notice within 21 days of discovering such conditions. While written notice of claims should always be provided, a recent court decision drew an important distinction between the AIA General Conditions’ concealed conditions clause and those clauses pertaining to other types of claims. Although the General Conditions specifically require written notice of most claims, this decision illustrates that mere verbal notice of a differing site conditions claim will suffice under its terms. Robert W. Carlstrom Co. v. German Evangelical Lutheran St. Paul’s Congregation of the Unaltered Augsburg Confession at Jordan, 662 N.W.2d 168 (Minn. Ct. App. 2003).

In 1997, a church began exploring a roof-reconstruction project. Prior to bidding, interested contractors were allowed to inspect portions of the roof. For various reasons, the church refused to remove attic insulation for inspection, thus denying access to a substantial portion of the roof. Following a competitive bidding process, a contractor was awarded a contract for the project valued at $213,900.

The contractor’s crew began removing the old roof and was surprised by the poor condition of the roof’s underlying framing. The contractor concluded that, because of the depth of bird-mouth cuts in the roof’s framing and of the roof's bizarre blocking, additional work, material and labor would be required to complete the project.

The contractor contacted the architect and verbally reported the unusual condition of the roof. After determining it would need to do additional work, the contractor also immediately gave verbal notice to the church of the problem. Several days later, the contractor verbally reported the condition of the roof to the church's building committee, this time outlining the expected delays and additional costs necessary to correct the conditions.

Approximately three months after the contractor’s verbal presentation to the committee, the contractor submitted a "change order request" seeking an additional $51,680.94. This request represented the first written documentation submitted by the contractor concerning the unknown condition of the roof. The church's architect concluded that the condition of the roof constituted a concealed or unknown condition and recommended that the church pay the additional funds. The church refused to make the additional payment, claiming that the contractor was required under the contract to submit written notice of the concealed or unknown conditions.

Both parties proceeded to litigation, each alleging breach of contract. The trial court found that the contractor encountered unknown conditions materially different from conditions commonly found in similar buildings. The trial court further concluded that the contract did not require immediate written notice of these unknown conditions and held that the contractor’s verbal notices satisfied the obligation to report these conditions within 21 days after discovery.

On appeal, a higher court considered the trial court’s decision and noted that the clause of the AIA General Conditions concerning claims for concealed conditions is distinguishable from other clauses of the General Conditions concerning claims for extra cost or time. According to the General Conditions, if conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions, differing materially from those indicated in the contract, or (2) unknown physical conditions of an unusual nature, differing materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the contract, then notice by the observing party shall be given to the other party promptly before the conditions are disturbed and in no event later than 21 days after first observance of the conditions. Unlike other provisions of the General Conditions concerning claims, this clause does not specifically require written notice of a claim within 21 days of discovery. In fact, written notice is not required until after the architect has investigated the site (following the contractor’s initial notice) and determined whether there is a basis for a claim. Applying the terms of the contract literally, the court suggested that the unique requirements of the concealed conditions clause were meant to ensure that possible design changes stemming from concealed conditions were quickly investigated and addressed. Accordingly, the appellate court agreed with the trial court and concluded that the contract with the church did not require immediate written notice of the concealed roof condition.

When a contractor discovers concealed or subsurface conditions for which it intends to submit a claim, the contractor must ensure that notice is timely provided in the manner required by its contract. While it is good practice to always provide such notice in writing, courts will hesitate to require written notice when not specifically required by the contract. As shown in the case of Robert W. Carlstrom Co., even preprinted forms such as the AIA General Conditions may permit verbal notice, unless modified by the parties. Familiarity with the forms commonly employed in your trade is the best way to recognize and negotiate favorable claim and disputes clauses.

FEDERAL COURT FINDS THAT HOME OFFICE OVERHEAD EXPENSES MAY BE RECOVERED EVEN IF CONTRACT PERFORMANCE IS NEVER BEGUN

In Nicon, Inc. v. United States, 331 F.3d 878 (Fed. Cir. 2003), the U.S. Court of Appeals for the Federal Circuit held that a contractor may recover home office overhead expenses upon its termination for convenience by the government even when it had not yet begun performance at the time of termination. While this decision represents welcome news for contractors delayed prior to commencement of performance, the court cautioned that the Eichleay Formula, a popular means of calculating home office overhead damages, is not appropriate in such situations.

In Nicon, the United States awarded a remodeling contractor a $1.4 million contract to repair an Air Force Base dormitory at MacDill Air Force Base in Hillsborough County, Florida. Three days after the award, a disappointed bidder filed a bid protest. The government then notified the contractor of the protest and instructed it to take no further actions as to the preparation and forwarding of submittals. After a 288-day delay, and before the government issued a notice to proceed, the government terminated the contractor’s contract for convenience. Thus, in Nicon, the contractor never commenced performance.

In the settlement negotiations that followed, the contractor asserted a claim for unabsorbed home office overhead using a modified version of the Eichleay formula. While the contracting officer awarded the contractor $184,757 for its direct costs, related overhead, and profit, he denied the contractor’s $387,513 Eichleay claim for unabsorbed home office overhead. The contractor disputed the denial of this portion of its claim, but the trial court granted summary judgment in the government’s favor. The trial court reasoned that, while Eichleay damages are available when a delay extends contract performance, in this case, there was no performance period to extend.

On appeal, the Federal Circuit Court agreed that Eichleay damages were improper because there was no touchstone on which to meaningfully measure how long the delay extended performance of the contractor’s work. According to the appellate court, to use Eichleay to quantify a home office overhead claim, a contractor must show an owner-caused delay of uncertain duration, that the delay extended the contract time and that it was standby and unable to take on other work during the delay. Then the burden shifts to the owner to show either that the contractor could have obtained "replacement work" during the delay or that the contractor's inability to obtain replacement work was caused by a factor other than the owner’s delay.

Here, because the contractor had no actual "contract billings" or "days of performance" to use for Eichleay purposes, it proposed that the court both: (1) substitute constructive figures; and (2) assume that, if the contractor had commenced the work, it would have completed the project on time. The court found, however, that constructive figures may not be used in an Eichleay calculation, writing that “[u]se of the Eichleay formula is an extraordinary remedy, and we have been very reluctant to make a drastic shift in the circumstances under which the Eichleay formula has been available."

Despite this, the court did not disallow the contractor’s claim entirely, holding that pre-performance home office overhead expenses may be awarded in termination for convenience situations provided that: (1) a “reasonable method of allocation” is available under the facts; and (2) all of the other strict requirements for entitlement to such expenses are met. The court held that the Eichleay formula may not be modified to apply to situations in which there is no contract performance, but stressed that the overall purpose of a termination for convenience settlement is to fairly compensate a contractor for the costs it incurs in connection with the terminated work. Thus, if an owner doesn’t issue a notice to proceed within “a reasonable time” after the award of the contract, and the contract does not set a required date for the notice to issue, unabsorbed home office overhead is properly recoverable even if the contract is terminated before contract performance begins. The court remanded the case to the trial court to find a non-Eichleay basis to compensate the contractor for its unabsorbed home office overhead.

As a practical matter, Nicon supports the general principle that, in a termination for convenience, the law seeks to make whole the affected contractor, and thus an unabsorbed home office overhead is a valid claim if the factual circumstances support it.


VIRGINIA COURT INVALIDATES MULTI-MILLION DOLLAR
CLAIM DUE TO CONTRACTOR’S FAILURE TO GIVE TIMELY NOTICE

Most construction contracts contain language obligating the contractor to submit claims for extras or changes to the owner or higher-tier contractors within a certain period of time after it incurs increased costs or delay. In addition, many contracts also require the contractor to notify the owner or higher-tier contractors of its intention to ultimately make such claims within a certain period of time after the event giving rise to the claims. As demonstrated by MCI Constructors v. Spotsylvania County, 2003 Va. Cir. LEXIS 115 (Spotsylvania County Cir. Ct. 2003), it is critical for contractors to understand the precise moment when the time period to take action on a claim will begin to run. Adopting an unreasonable or unrealistic view of the triggering event can have disastrous consequences.

In MCI Constructors, a contractor was engaged by Spotsylvania County to construct a water treatment facility. As work progressed, disputes arose between the county and the contractor, delays occurred and extra work was required. During the course of this project, the contractor submitted various change orders to the county for approval, several of which were rejected. Months after the project was scheduled to be completed, the contractor submitted a “Request for Equitable Adjustment” to the County, requesting additional payment of more than $9 million and an eight-month time extension for the changed and extra work it performed. The County disputed 93 of the 106 claims asserted within the Request on the grounds that, among other things, the contractor failed to give timely notice of its intention to submit such claims. In response, the contractor brought suit to recover on its claims.

The trial court first examined the provisions relevant to the timing of the contractor’s notice. The court found that the contract between the County and the contractor provided that no claim for changed or extra work could be made against the County unless it was notified of the contractor’s intention to present such claim “within ten days of the event, thing, or occurrence giving rise to the alleged claim.” Similarly, state and local laws required the contractor to provide written notice of its intention to file a claim within ten days of the occurrence or beginning of the work upon which the claim was based.

The court next examined when the “event” or “occurrence”, which triggered the contractor’s duty to notify the county of its intention to present a claim for extra or changed work, happened. The County argued that the contractor was required to notify the County even before a dispute arose — in effect, simultaneously with its submission of a proposed change order in response to a request or directive in the field. The contractor took an opposite view, arguing that it was entitled to wait until a full-fledged dispute had arisen, and it was able to precisely determine the monetary impact of the extra or change, before having to provide notice of its intention to submit a claim. The court rejected both arguments, instead concluding that, as to each claim, the triggering event for the notice requirement was the contractor’s learning that its proposed change order, or other request for adjustment of contract terms, was denied, disallowed, or disapproved, in whole or in part, by the County. Applying such standard, the court concluded that the contractor did not give the County timely notice of its intent to submit all 93 disputed claims, and thus held that those claims were barred.

Contractors should always be careful to comply with all notice requirements in their contracts. In order to do so, contractors need to have (1) a firm grasp on the time period(s) in which they must take action to preserve their claim and (2) a good understanding of the point of which those periods will begin to run.