|
 |
 |
 |
 |
 |
 |
| |
November/December
2006 Newsletters
Katz & Stone,
L.L.P. Construction Newsletter
November/December 2006
SUBCONTRACTOR UNABLE TO
LIEN OWNER’S PROPERTY
WHERE SUBCONTRACTOR PERFORMED WORK FOR OWNER’S LESSEE
Mechanic’s lien
statutes provide a valuable tool for protecting subcontractors from
owners and contractors who refuse to pay their
subcontractor’s for work performed. However, as the
case of R.T.B.H. v. Simon Property Group, 849
N.E.2d 764 (Ind. 2006) demonstrates, subcontractors who performs work
for a lessee may in some circumstances be unable to lien the
owner’s interest in the property. Typically, when a
contractor performs work for a lessee, the contractor can only obtain a
lien against the property interest of the lessee as opposed to the
owner’s property interest.
In R.T.B.H.,
a lessee entered into a lease at a shopping mall with the
owner—the term of the lease was twenty years with an option
to renew. The lease required the lessee to demolish a
cafeteria and department store already located on the property, and
construct a new retail store. The lessee hired a general
contractor, who in turn hired a subcontractor to perform window and
glass work. The lessee bore the expense of the construction
beyond the initial demolition and the owner’s role in the
project was limited to approval of the lessee’s
plans. Upon completion of the project, the general contractor
refused to pay the subcontractor for its services and filed suit
against the subcontractor for damages. When the
subcontractor filed a mechanic’s lien against the property,
the contractor moved to dismiss the lien. The trial court
removed the lien and the subcontractor appealed.
The court noted that in
order for the subcontractor to assert a mechanic’s lien
against the owner’s property, the subcontractor must have
performed its work under the authority and per the direction of the
owner. In addition, there must be more than merely inactive
or passive consent on the part of the owner. Otherwise, the
subcontractor would be limited to claiming a lien against the
lessee’s interest in the property.
The court commented on
three factors which must be taken into consideration when making its
determination. First, a reviewing court could evaluate the
degree of the owner’s active participation in the decisions
and the actual construction (i.e., payments from
the owner directly to the general contractor usually satisfied active
participation). Second, the court should determine how
closely the improvements in question resemble a directly bargained-for
benefit. In the instant case, the fact that the landlord
could take back the building (with the improvements) in 20 years and
the fact that the income from the new store would assist the lessee in
making its payments to the owner were not enough to indicate that a
bargained-for benefit occurred. Third, a court should
consider whether the owner actively consented to the improvements and
whether the owner would be unjustly enriched by the improvements if the
lessee defaulted in its lease. In other words, if an owner
leases to a tenant who is of dubious financial means while at the same
time requiring the tenant to make improvements, then this would provide
an equitable rationale to permit a mechanic’s lien against
the owner’s property interest. This was not the
case here as the lessee was not of uncertain financial
responsibility. Ultimately, the court determined that the
subcontractor could not maintain a mechanic’s lien against
the owner’s property interest.
As R.T.B.H. demonstrates,
subcontractors may not always be able to enforce a mechanic’s
lien against the owner’s property if the party contracting
for improvements is a lessee and not the owner. Thus, as a
practical matter, any party entering into a contract for construction
should determine whether or not the apparent
“owner” of the project actually owns the real
property or is merely a tenant. If the latter is the case,
the subcontractor may not be able to claim a lien against the property
unless certain factual circumstances, which tend to show that
improvements were performed for the benefit of the owner and the owner
took an active role in the construction of the improvements, hold true.

COMMERCIAL GENERAL
LIABILITY POLICY COVERS
DAMAGE TO GENERAL CONTRACTOR’S NON-DEFECTIVE
WORK CAUSED BY SUBCONTRACTOR’S DEFECTIVE WORK
Although a commercial
general liability (CGL) policy may not provide liability coverage for a
general contractor to correct defective work performed by a
subcontractor, such a policy may provide liability coverage for the
cost to remedy unexpected/unintended property damage to the
contractor’s otherwise non-defective work which was caused by
a subcontractor’s defective work. This point is
illustrated in French v. Assurance Co. of Am.,
448 F.3d 693 (4th Cir. 2006).
In this case, a homeowner
contracted with a general contractor for the construction of a
single-family home. The general contractor enlisted a
subcontractor to install a synthetic stucco Exterior Insulating
Finishing System (EIFS) on the house. Five years after the
homeowners moved into the house, they discovered extensive moisture and
water damage to the structure and walls of their house; such damage
resulted from defective installation of the EIFS.
After the homeowner filed
suit against the general contractor, the general contractor looked to
its CGL carrier for coverage for both the defective EIFS and the damage
caused by the water infiltration into the underlying structure and
walls as a result of the defective EIFS. The CGL carrier
denied coverage based upon several exclusions contained in the CGL
policy. The CGL policy provided that the CGL carrier would
defend and, if necessary, indemnify the general contractor for property
damage only if such damage was caused by an
“occurrence,” or if not otherwise excluded by the
terms of the policy. The CGL policy defined an
“occurrence” as “an accident, including
continuous or repeated exposure to substantially the same general
harmful conditions.” The CGL policy also contained
an exclusion limiting coverage for property damage that was
“expected or intended from the standpoint of the
insured.”
The homeowners (as
assignees of the general contractor’s rights under the
policy) argued that the CGL policy provided coverage for both the
defective EIFS and the damage caused to the structure and walls because
of the defective EIFS. The CGL carrier argued that the CGL
policy’s exclusions foreclosed coverage for all of the
homeowner’s damages.
The court found that the
CGL policy did not provide coverage for the defectively installed
EIFS. The court ruled that the defective installation of EIFS
to the exterior of the house did not constitute an
“accident,” and therefore, it did not constitute an
“occurrence” under the CGL policy. First,
the court noted, “An act of negligence constitutes an
‘accident’ under a liability insurance policy when
the resulting damage takes place without the insured's actual foresight
or expectation. The test is a subjective one, because . . .
if it were to adopt an objective standard and hold that the term
‘accident’ as used in liability insurance policies
excluded coverage for damage that should have been foreseen or expected
by the insured, such insurance policies would be rendered all but
meaningless.” The court reasoned that if the
damages the homeowner suffered related to the satisfaction of the
contractual requirements, the damages were not unexpected. In
other words, if a general contractor delivered a house that did not
meet the contractual requirements, it would not be unexpected or
unforeseen that such defects would occur from the standpoint of the
general contractor. No coverage existed for this element of
the homeowner’s
claim.
However, the court did
find that the CGL policy provided coverage for the damage to the
non-defective structure and walls of the house caused by water
infiltration through the defectively-installed EIFS. In
reaching this conclusion, the court emphasized that there was no
evidence or allegation that upon completion of the house, any defect
existed with respect to the structure or the walls. The
record showed that the structure and the walls were subject to
infiltration over a period of five years as a result of the defective
EIFS exterior which allowed water intrusion into the house.
As such, there was no evidence that the general contractor could have
expected or intended that that non-defective structure and walls of the
house would be damaged as a result of water intrusion.
Further, there was no allegation that the general contractor either
expected or intended its subcontractor would defectively install the
EIFS on the exterior of the house. As such, the court found
that the water intrusion into the house was an
“accident,” and therefore an
“occurrence,” under the CGL policy; no exclusion in
the policy precluded coverage.
Accordingly, the court
ruled that while the CGL policy did not provide coverage for the
defective EIFS itself, the policy did provide coverage for the damage
to the structure and walls caused by water infiltration resulting from
the defective installation of the EIFS. As a result of this
case, general contractors should review their CGL policies to determine
what coverage their policies provide in the event that a
subcontractor’s defective work causes damage to other work on
a project. Additionally, owners should also review their
contractors’ CGL policies in the event that the owner is
assigned a contractor’s rights under the policy.
MISSOURI COURT FINDS
CONTRACT FOR CONSTRUCTION
CONTAINING APPROXIMATE PRICE INVALID AND UNENFORCEABLE
Sometimes contracts for
construction are entered into with the express understanding that the
total price, or the scope of the work, will be agreed subsequent to
execution of the contract. However, if such a contract does
not clearly evidence a mutuality of agreement between the parties
regarding the essential terms of the contract, a court may find that
the contract is invalid and unenforceable. This principle is
demonstrated in Olathe Millwork Co. v. Dublin,
189 S.W.3d 199 (Mo. 2006).
In Olathe
Millwork, the homeowners entered into an agreement with a
general contractor for the construction of a new home; the
homeowners’ prior home was destroyed by a fire. The
agreement stated that the general contractor was to provide labor,
materials and equipment for the construction of the new home.
Although blueprints were submitted to the general contractor, no
specifications corresponding to the blueprints were ever prepared by an
architect or an engineer and submitted to the general
contractor. Instead, the general contractor and the
homeowners relied upon an itemized breakdown of allowances prepared by
the homeowners’ insurance company as the
“contractual specifications.” The total
cost to the homeowners for the construction of the new home was listed
in the agreement as approximately $270,000.00.
After construction commenced, various disputes arose between the
general contractor and the homeowners. As a result, the
homeowners withheld interim progress payments due the general
contractor. Eventually, the homeowners filed suit against the
general contractor for breach of contract; the general contractor filed
a counterclaim for breach of contract, among other claims.
The trial court found that a valid contract existed and awarded both
the general contractor and the homeowners damages for breach of
contract (the general contractor received an award of damages which was
merely reduced by the amount awarded to the homeowners).
On appeal the general
contractor argued, among other arguments, that the trial court erred in
finding that the parties had entered into a valid contract.
Specifically, the general contractor argued that an express contract
did not exist because the essential terms of the agreement for
construction of the new home had been reserved for future
determination—the parties had not reached an agreement as to
the contract price and the scope of the plans.
The Court of Appeals of
Missouri first noted that in order for a valid contract to exist,
mutuality of agreement must exist. Mutuality of agreement
requires “a mutuality of assent or a meeting of the minds to
the essential terms of the contract.” The court
continued, the long standing rule in Missouri is that a contract must
include a definite price to be valid and enforceable.
Further, a valid contract does not exist if the essential terms of the
contract are reserved for the “future determination of both
parties.”
After restating these
general principles, the court addressed the general
contractor’s argument that the parties had not entered into a
valid and enforceable contract. First, the court observed
that the parties used an approximate value as a place holder for the
true contract price because they did not know the final cost of the new
home. Second, the court found that the parties had not
reached a clear agreement as to the specifications for the work to be
performed because no specifications were ever submitted to the general
contractor. Third and finally, the court noted that the new
home that was eventually built was substantially larger and contained
many upgrades as compared to the itemized allowances prepared by the
homeowners’ insurer. Therefore, the homeowners and
the contractor did not have a valid contract. The trial court
erred in finding that a valid contract existed.
As Olathe
Millwork demonstrates, courts are not likely to find that
two parties have entered into a valid and enforceable construction
contract where there is no mutuality of agreement regarding essential
terms of the contract such as the contract price or the scope of the
work to be performed pursuant to the contract. Therefore, any
party who enters into an agreement for construction without defining
all essential terms should be cognizant that such an agreement may not
be valid and enforceable.
D.C. COURT APPLIES
ECONOMIC LOSS DOCTRINE
TO BAR NEGLIGENCE CLAIM BY SUBCONTRACTOR’S
SURETY AGAINST SUPPLIER AND THE SUPPLIER’S SURETY
In most cases, an act of
negligence by a contractor on a construction project also constitutes a
breach of its contract. However, as established in RLI
Insurance Co. v. Pohl, Inc., of America, 2006 U.S. Dist.
Lexis 45958 (D.D.C. July 7, 2006), the economic loss doctrine prevents
the recovery of certain damages under the tort claim of negligence even
though such damages would be recoverable under a breach of contract
claim.
In RLI,
the subcontractor was retained by the general contractor to install
zinc panels on the façade of the owner’s
building. Pursuant to the subcontract, the
subcontractor’s surety issued a performance bond.
The subcontractor then contracted with the supplier to fabricate the
panels, and the supplier’s surety also issued a performance
bond. After the panels were installed, the owner and general
contractor discovered defects in the panels and demanded that they be
replaced. The subcontractor subsequently defaulted, and the
subcontractor’s surety was called upon to complete
performance. The subcontractor’s surety demanded
that the supplier replace the rejected panels, but the supplier refused
unless new panels were ordered and paid for in full. To
satisfy the owner, the general contractor ultimately ordered
replacement panels directly from the supplier, paid full price, and
charged the subcontractor’s surety for such cost.
The subcontractor’s surety then brought suit against the
supplier and the supplier’s surety alleging negligence, among
other claims; the defendants moved to dismiss that tort
claim.
In its negligence claim,
the subcontractor’s surety alleged that the defendants owed a
duty of care to ensure that the contract between the subcontractor and
supplier was successfully completed, and that the defendants breached
such duty by negligently fabricating the zinc panels. As a
result the defendants would owe certain amounts to cover the costs to
repair or replace the panels. However, the court ruled that
the negligence claim failed because such damages are not recoverable in
tort under the District of Columbia’s economic loss
doctrine. The economic loss doctrine provides that a
plaintiff cannot recover, in tort,
for purely economic losses (i.e., the loss of
value or use of a product itself, the cost to repair or replace the
product, or the lost profits resulting from the loss of use of the
product). This is particularly true where a contract exists
that governs the available remedies for such
losses. Here, the court concluded, the
subcontractor’s surety sought such purely economic losses, in
the form of the costs to repair, cure, remedy and replace the defective
panels. Moreover, there was a contract in place between the
subcontractor and supplier which governed the supplier’s
obligation to properly fabricate the panels, as well as any breaches of
that obligation. Accordingly, the court dismissed the
subcontractor’s surety’s negligence claim because
District of Columbia law does not allow for the recovery of purely
economic losses in a contract setting under a theory of negligence.
As RLI
shows, even if a contractor’s negligent acts cause a breach
of a construction contract, the injured party cannot necessarily
recover the same damages under a negligence claim as compared to a
breach of contract claim. If the economic loss doctrine
applies, as it does in most states, a plaintiff can only seek purely
economic losses through its contractual remedies. Where there is no
privity of contract between the plaintiff and defendant, economic
losses cannot be recovered in tort.
|
|
 |
 |
 |
|