Katz & Stone, L.L.P.'s law practice is devoted to helping the construction industry resolve construction contract problems and disputes. Our attorneys have worked on a wide variety of construction assignments as represented by the following examples:

United States

R.W. Granger & Sons, Inc. v. J&S Insulation, Inc., United States Fidelity & Guaranty, Boston, Massachusetts, 2001 - Katz & Stone represented a fireproofing and insulation subcontractor, J&S Insulation, Inc., against a surety, USF&G, in the subcontractor’s successful recovery from the surety of compensatory damages, punitive damages, and attorneys’ fees and costs. The subcontractor’s claim arose out of the surety’s failure to conduct a good faith investigation of, and then settle, the subcontractor’s payment bond claim, which had been filed under Massachusetts’ Little Miller Act. After the subcontractor prevailed at the trial level, the surety appealed directly to the Massachusetts Supreme Judicial Court, which unanimously affirmed the trial court decision in favor of the subcontractor. In addition to affirming the trial court’s judgment, the Massachusetts Supreme Court also awarded the subcontractor appellate attorneys’ fees and costs it incurred defending the appeal. With Katz & Stone, L.L.P.’s assistance, the subcontractor recovered more than $1.5 million on what was originally a $203,000 claim.

Shenandoah Valley Regional Airport v. S.P. Cahill, Inc. and Mountbatten Insurance, Shenandoah, Virginia, 2000 - Katz & Stone represented the public airport owner against the contractor and surety in the successful recovery of a claim arising from the performance of defective concrete work in the construction of private aircraft hangars.

Pray Construction Company v. Frontier Insurance, Charleston, West Virginia, 2000 - Katz & Stone represented the general contractor in the successful mediation and recovery of a reprocurement claim on a defaulted subcontractor's performance bond.

Kennecott Utah Copper Corporation v. Industrial Constructors Corporation, Salt Lake City, Utah, 1998 - Katz & Stone provided claims analysis and defense consultation to Kennecott Utah Copper Corporation in connection with numerous claims submitted by Industrial Constructors Corporation, the earthworks contractor on the Tailings Modernization project, a $200+ million construction project located near Salt Lake City, Utah.

Veterans Administration Hospital, Baltimore, Maryland, 1997 - Katz & Stone represented the mechanical subcontractor, Pierce Associates, Inc., in the successful resolution of a claim for lost efficiency and productivity resulting from significant errors and omissions in the mechanical design documents for a multi-million dollar hospital.  Particularly helpful in settling the claim was the analysis provided by Katz & Stone correlating lost efficiency damages to impacts in the field installation of the mechanical work.

Kajima International, Inc. v. Harborview Limited Partnership, Baltimore, Maryland, 1997 - Katz & Stone represented Kajima International, Inc., the general contractor, in a complex litigation against the developer of a 27-story luxury condominium complex in Baltimore. Katz & Stone helped the general contractor initially obtain an interlocutory mechanicÕs lien in the amount of $1.65 million to secure its payment claim. Then, through summary judgment motions, Katz & Stone achieved the dismissal of 85 % of the ownerÕs claims, including those based upon alleged defective work and delays to substantial completion on the condominium project. Shortly after the courtÕs ruling on the summary judgment motions, the matter was successfully settled for the client.

Alcon Demolition, Inc. v. The Clark Construction Group, Washington, D.C., 1995 - Katz & Stone represented the demolition and asbestos abatement subcontractor in the successful reversal of a default termination on a major World Bank project in Washington, D.C.  The main contractor's reprocurement claim in the amount of approximately $2 million was rejected in its entirety.

Commerce Place, Baltimore, Maryland, 1995 - Katz & Stone represented the general contractor, Kajima International, Inc., in a successful arbitration proceeding arising out of the construction of a 30-story office building located in downtown Baltimore. Katz & Stone assisted the general contractor in the recovery of its contract balance and numerous change order claims, and successfully defended the contractor against the ownerÕs counterclaims for defective work and delays.

Friant-Kern Power Generation Project, Visalia, California, 1986 - Katz & Stone represented Commercial Contracting, Inc., a rigging contractor headquartered in Troy, Michigan, in this complex multi-party construction litigation arising out of the installation of turbine and other power generating equipment at the Friant-Kern Dam in Tulare County, California.  Among the issues presented were whether the client's scope of work had changed from that bid in view of the fact that the equipment delivered for installation by the rigging contractor proved to be significantly larger and heavier, and consisted of more components, than as represented in the bid documents.  Further complicating the situation was the fact that the principal contractor defaulted and the project was taken over by the surety who retained a completion contractor.  Claims were asserted by and among the owner, the engineer, the defaulted contractor, the surety, the replacement contractor, the equipment manufacturer and the rigging contractor.  After lengthy pretrial discovery and mediation, the matter was successfully settled for the client.

St. Joseph's Hospital, Louisville, Kentucky, 1984 - Katz & Stone's senior partner assisted the general contractor and mechanical and electrical subcontractors in recovering on a consolidated claim for errors and omissions in the contract documents which severely impacted construction of a large private hospital.

Dallas City Hall, Dallas, Texas, 1983 - Katz & Stone's senior partner assisted the general contractor of this I.M. Pei-designed project (consisting of 90,000 cubic yards of architectural-grade post-tensioned concrete) to recover a claim for delay and lost efficiency owing to errors and omissions in the contract documents and constructive changes.  Also included in the successful recovery were the claims of the mechanical and electrical contractors whose work was similarly impacted by the design documents.

Cedars-Sinai Medical Center, Los Angeles, California, 1979 - Katz & Stone's senior partner assisted the mechanical subcontractor in the successful prosecution of a multi-million dollar claim arising out of errors and omissions in the contract drawings.  As a result of significant design problems, the mechanical subcontractor's work was severely delayed and disrupted, resulting in claims for delay damages and lost productivity.  Proof of the mechanical  subcontractor's damages required the review, assimilation and use of thousands of documents bearing upon the subcontractor's work, particularly in the hospital's interstitial levels where much of the subcontractor's work was installed.



Bermuda

Ace Insurance Headquarters, Bermuda, 2000-2001 - Working with the owner's representative, Katz & Stone has provided advice and consultation relative to various construction issues during project performance including contract negotiation and interpretation and the analysis of claims submitted by the main contractor.

Sea-Land Construction Ltd. and Bermuda Underwater Exploration Institute, Bermuda, 2000 - Katz & Stone represented the general contractor in an arbitration arising out of the construction of a museum located in Bermuda and devoted to underwater exploration.  Issues included the impact of numerous variations on the project schedule, lost productivity and the contractor's resulting increased costs.  A settlement favorable to the contractor followed several appearances before the arbitrators and prior to hearings.

Burland, Conyers & Marirea and Landmark Restoration, Inc., Bermuda, 1992 - Katz & Stone represented Burland, Conyers & Marirea in an arbitration arising out of construction of the new Bermuda Airport terminal.  The dispute involved the default termination of the specialty contractor for the roofing system.  Working closely with expert roofing consultants, Katz & Stone assisted the main contractor in establishing the validity of the termination and reprocurement costs to complete the defaulted specialty contractor's work.


Caribbean

Johnston International Limited and Needham’s Point Holdings, Ltd, Barbados, 2002 – 2004 – Katz & Stone is providing advice and representation to Johnston International Limited, the main contractor on the Barbados Hilton Hotel project owned by Needham’s Point Holdings Limited. Katz & Stone’s work on behalf of Johnston International Limited includes representing Johnston International Limited in an arbitration initiated against the owner of the project in regard to claims for delay, disruption and changes in the scope of work.

Damus Limited and Bechtel, Trinidad, 2004 – CCAS is providing advice to Damus Limited, a specialist piping contractor, on a substantial LNG project located in Trinidad. Our advice has included subcontract review and assistance in regard to a major work stoppage which has impacted Damus’ work.

Damus Limited and VA Tech Voest MCE GmbH, Trinidad, 2003 – CCAS provided advice to, and representation of Damus Limited, a specialist piping contractor on a methanol project located in Trinidad, in connection with a dispute between Damus and VA Tech Voest MCE GmbH over the application of contract provisions dealing with an overrun in estimated quantities.

Trinidad Contractors, Ltd. and Government of British Virgin Islands, British Virgin Islands, 2003 – CCAS provided an opinion supporting the recovery of time-related costs resulting from delays to construction of a portion of the works at the Lettsome Airport, B.V.I. Our opinion extended to an analysis of the time-related costs associated with delays to the client’s performance and justification for the recovery of such costs under the contract documents and principles of English construction contract law.

Roberts Construction & Engineering Co., Ltd., Antigua, 2003 – CCAS provided an opinion on the recovery of loss and expense and extension of time resulting from delay in the construction of a luxury residence in Jumby Bay, Antigua.

Trinidad Contractors, Ltd. and Government of Grenada, Grenada, 2003 – CCAS provided an opinion supporting the recovery of a time extension and time-related costs resulting from delays to the Gouyave Sea Defence project, the installation of an armoured rock sea wall, caused by the failure of the employer to provide accurate design documents.

Design Collaborative, Tobago Hilton Hotel, Trinidad and Tobago, 2002 – CCAS provided advice to the design team on final cost certification and related project close-out issues.

C.O. Williams, Inc., Grantley Adams International Airport, Barbados, 2002 – CCAS provided the paving contractor with an opinion on the recovery of additional costs resulting from delay to and disruption of the works.

Ace Insurance Headquarters, Bermuda, 2000-2001  — Working with the owner’s representative, Katz & Stone has provided advice and consultation relative to various construction issues during project performance including contract negotiation and interpretation and the analysis of claims submitted by the main contractor.

Sea-Land Construction Ltd. and Bermuda Underwater Exploration Institute, Bermuda, 2000 — Martyn Bould was appointed one of three arbitrators by claimant, a Bermuda-based general contractor, to decide various performance issues arising out of the construction of a museum located in Bermuda and devoted to underwater exploration.  Katz & Stone represented the contractor.  Issues included the impact of numerous variations on the project schedule and the contractor’s resulting increased costs.  The matter was settled by agreement of the parties after several appearances before the arbitrators and prior to hearings.

Andro Electric Co., Ltd. and Noell, Inc., Grand Cayman, 1998  — Katz & Stone represented Andro Electric Co., Ltd., the electrical subcontractor, in the resolution of claims against the main contractor on the Caribbean Utilities Company project.

Burland, Conyers & Marirea and Landmark Restoration, Inc., Bermuda, 1992  — Katz & Stone represented Burland, Conyers & Marirea in an arbitration arising out of construction of the new Bermuda Airport terminal.  The dispute involved the default termination of the specialty contractor for the roof.  Working closely with expert roofing consultants, Katz & Stone assisted the main contractor in establishing the validity of the termination and reprocurement costs to complete the defaulted specialty contractors’ work.